Temple, TX Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger threshold
1 acre or more disturbed
Large activity threshold
5+ acres disturbed
BMPs required before
site establishment begins
First-offense fine
$250 minimum
Max civil penalty
$5,000 per day

Summary

Temple requires construction sites disturbing an acre or more to install erosion and sediment control BMPs before work begins, per Chapter 27 Stormwater.

An operator of a construction site regulated under this Chapter must implement best management practices to control and minimize the discharge into the MS4, waters of the United States, and state water of any sediment, silt, earth, soil, or other material from the construction site. Erosion control elements meeting the criteria for best management practices must be installed before any construction site is established in accordance with an installation schedule as specified in a stormwater pollution prevention plan required by the construction general permit or individual permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Reformat).

Full Breakdown

Any small (1-5 acres) or large (5+ acres) construction activity in Temple must implement best management practices to keep sediment, silt, earth, and soil out of the storm drain system, waters of the U.S., and state water. Erosion control elements meeting BMP criteria must be installed before the site is established, following the schedule in the required stormwater pollution prevention plan (SWPPP). Operators must also obtain any applicable TCEQ construction general permit and post site notices.

Violations & Fines

Class C misdemeanor: fines of $250 (1st), $500 (2nd), $1,000 (3rd and each thereafter), capped at $2,000 per violation; city may also pursue civil penalties up to $5,000/day and stop-work orders.

Frequently Asked Questions

When must erosion controls go in at a Temple construction site?
Before the construction site is established, on the installation schedule set in the site's stormwater pollution prevention plan.
What size projects does Temple's erosion rule cover?
Any activity disturbing 1 acre or more, including phased or multi-operator projects on a common plan over 5 acres.

Sources & Official References

Other rules in Temple

All Temple rules

Texas rules heatmap·Compare Temple to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Temple, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Bell County handle erosion control.

Killeen, TX
Some Restrictions