Key Facts

Duty holder
Permittee under grading/stormwater permit
Core rule
Prevent sediment/dust discharge off-site
BMP maintenance
Kept until final stabilization
Final stabilization
70% pre-disturbance vegetative cover
Plan required
Erosion/sediment control plan with grading application
Enforcement
Stop-work order, security deposit draw

Summary

Under City Code Section 22-156(5), anyone holding a Thornton grading or stormwater quality permit must stop sediment and dust from leaving the site using temporary and permanent best management practices, maintain those measures until the site is fully stabilized, and remove them once vegetation is established. Projects disturbing more than an acre also need a state discharge permit or sediment control plan before construction begins.

Erosion, sediment, and dust control. The permittee shall be responsible to prevent discharge of sediment or dust from the site to any watercourse, drainage system, or adjacent property by implementing temporary and permanent BMPs and to protect from all damage that may result from wind, erosion, or sedimentation from the site. The permittee shall be responsible for maintenance of all temporary structural BMPs used to prevent discharge of sediment or dust from the site until final stabilization of all disturbed areas. Permittee shall promptly remove any temporary BMPs after final stabilization.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 65).

Full Breakdown

Section 22-156(5) of the Thornton City Code makes erosion, sediment, and dust control a direct duty of every permittee under a grading, stormwater quality, or floodplain permit. The permittee must prevent sediment or dust from reaching any watercourse, drainage system, or adjacent property by implementing temporary and permanent best management practices (BMPs), and must maintain every temporary structural BMP until 'final stabilization' of all disturbed ground, defined in Section 22-112 as uniform vegetative cover of at least 70 percent of pre-disturbance plant density, or an equivalent permanent erosion-reduction method.

Once that stabilization threshold is reached, the permittee must promptly remove the temporary controls. Section 22-184 backs this up at the project-approval stage: no construction or building permit may issue for work disturbing more than one acre, or that is part of a larger common plan of development, until the applicant proves it has filed for a Colorado Discharge Permit System (CDPS) stormwater discharge permit, provided a sediment control plan, or shown the stormwater coordinator that no state permit is required. Every grading and stormwater application must include a preliminary or final erosion and sediment control plan under Section 22-141, and the city may attach erosion, sediment, dust, and noise-control conditions, plus requirements for haul routes and work-area traffic control, to any permit issued under Section 22-132(b).

If a permittee fails to control erosion or sediment to the city's satisfaction, Section 22-156(6) lets the city draw on the project's security deposit to remedy the condition or order all work stopped.

Violations & Fines

Failing to control erosion or sediment as required is enforced under Article V, Division 6. The development engineering manager can issue a stop-work notice under Section 22-196, giving the violator 24 hours to propose remedies and another 24 hours to implement them once accepted, or the city performs the corrective work itself and bills the responsible parties jointly and severally. Violations are also punishable under Section 1-8, with each day a separate offense.

Frequently Asked Questions

Who is responsible for erosion and sediment control on a Thornton construction site?
The permittee under the grading, stormwater quality, or floodplain permit, per Section 22-156(5). That person must install and maintain temporary and permanent best management practices to keep sediment and dust from leaving the site and reaching watercourses, drainage systems, or neighboring property, and must remove temporary controls once the site is fully stabilized.
When can temporary erosion control measures be removed in Thornton?
Only after 'final stabilization,' which Section 22-112 defines as uniform vegetative cover reaching at least 70 percent of pre-disturbance plant density, or an equivalent permanent erosion-reduction method being installed. Removing BMPs earlier leaves the permittee liable for any resulting sediment or dust discharge under Section 22-156(5).
Do I need a state permit in addition to Thornton's erosion control plan?
Yes, if the project disturbs more than one acre or is part of a larger common plan of development. Section 22-184 blocks issuance of a Thornton construction or building permit until the applicant proves it applied for a CDPS stormwater discharge permit or filed a sediment control plan with the city.

Sources & Official References

Other rules in Thornton

All Thornton rules

Compare Thornton to another location·View the Colorado environmental rules overview

Get notified when Erosion Control in Thornton, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.