Tuscaloosa, AL Environmental Rules: Erosion Control (2026)
Key Facts
- Size exemption
- None; applies regardless of development size
- Required standard
- Best management practices, state erosion handbook
- Protected waters named
- Lake Tuscaloosa, Lake Nicol, Harris Lake
- Enforcement authority
- City engineer; stop-work orders, civil sanctions
- Cost recovery
- City may bill violator for cleanup and restoration
- Governing ordinance
- Ord. No. 7075 (2007), amended through Ord. No. 9372 (2023)
Summary
Tuscaloosa requires erosion control best management practices on any development, earth change or driveway construction, no matter how small, to keep sediment out of streets, storm drains, Lake Tuscaloosa, Lake Nicol, Harris Lake, creeks and neighboring property. The city engineer can stop work and bill violators for cleanup.
Notwithstanding the fact that development activity on the property may be exempt from the requirements of a LDP or DLDP pursuant to the provisions of this article, any person causing any development, any earth change or constructing or reconstructing a driveway approach on any property, regardless of size, within the area shall take the necessary erosion control measures, utilizing best management practices, to provide for sedimentation facilities that prevent erosion and/or sedimentation in or upon city streets, public rights-of-way, public storm drainage facilities or public easements, public utilities, public water reservoirs (including Lake Tuscaloosa, Lake Nicol, and Harris Lake), creeks, rivers and streams and/or property of others. Best Management Practices shall be designed, implemented, and have maintenance performed as outlined in the Alabama Handbook for Erosion Control, Sediment Control and Stormwater Management on Construction Sites and Urban Areas, Volume 1 and 2.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 102).
Full Breakdown
Sec. 21-221, part of Article XII's land-development activities regulations, applies even to projects exempt from land-development or driveway permits: any person causing development, an earth change, or driveway approach construction on property "regardless of size" must take erosion control measures using best management practices to keep erosion and sedimentation out of city streets, rights-of-way, public storm drainage facilities, easements, utilities, public water reservoirs named specifically as Lake Tuscaloosa, Lake Nicol and Harris Lake, creeks, rivers, streams, and property belonging to others. Those practices must follow the state's Alabama Handbook for Erosion Control, Sediment Control and Stormwater Management on Construction Sites and Urban Areas, Volumes 1 and 2.
Enforcement runs through Sec. 21-223: the city engineer can issue a written notice to comply and a stop-work order, and continuing development or driveway work after a stop-work order is itself unlawful; the city engineer can also ask the city attorney's office to pursue civil sanctions. Subsection (c) separately makes it unlawful to allow dirt, silt, mud, debris or sediment to accumulate or discharge onto another's property, city streets, rights-of-way, storm drainage easements or facilities, or public water reservoirs because adequate erosion or sedimentation controls weren't provided or maintained.
If a developer or owner fails to remove sediment after written notice, Sec. 21-223(f) lets the city perform the cleanup and restoration itself and bill the responsible party for the full cost, and emergency situations allow city crews to remediate immediately without prior notice, with the invoice following afterward.
Violations & Fines
Failing to install or maintain adequate erosion or sediment controls, or continuing work after a stop-work order, is a misdemeanor under Sec. 21-223(b), punishable under Sec. 1-8. Allowing sediment to migrate onto city streets, rights-of-way, storm drainage facilities, public reservoirs or another's property is separately unlawful under Sec. 21-223(c), and the city can remove the sediment, restore the area, and bill the developer or owner for the full cost, including emergency cleanups performed without advance notice.
Frequently Asked Questions
Does every construction project in Tuscaloosa need erosion control, even small ones?
What standard do I have to follow for erosion control measures?
What happens if sediment washes off my site onto a neighbor's property or a city street?
Sources & Official References
Other rules in Tuscaloosa