Waco, TX Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

SWPPP trigger
Sites disturbing 1 acre or more, or part of larger project
Smaller-site plan
Erosion control plan required under 1 acre for most uses
Inspection frequency
Every 14 days, and within 24 hrs of 0.5in rain
C.O. hold
No certificate of occupancy until controls are complete
Responsible party
Owner, developer, builder or general contractor in control

Summary

Waco requires anyone disturbing an acre or more, or a smaller site inside a larger development, to file a stormwater pollution prevention plan and run erosion controls like silt fences, straw bales and stabilized entrances while building. Sites under an acre and outside a larger project still need a city erosion control plan for commercial, industrial, multifamily or subdivision work.

(a)The responsible party of any construction site within the city shall implement measures necessary to control erosion, sedimentation, debris, and stormwater pollution. The responsible party is responsible for the maintenance and performance of the temporary pollution control measures until permanent measures are in place. The pollution controls are designed to be selected by the developer based on the most cost effective and appropriate means to provide the required controls.(b)Temporary pollution control measures (during construction)...(1)Structural control of soil erosion.a.Stilt fences may be utilized, where necessary, to retain the sediments from disturbed areas within the site and decrease the velocity of sheet flows...c.Stabilized construction entrances shall be designed to reduce the amount of soil tracked off the construction site by vehicles leaving the site.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 88).

Full Breakdown

Chapter 26's stormwater article requires a site-specific stormwater pollution prevention plan (SWPPP) for any residential, commercial or industrial development that disturbs one acre or more, or a smaller parcel that is part of a larger common plan of development, under Sec. 26-326. That SWPPP must satisfy EPA or TCEQ construction general permit rules, identify the outfall into the city's storm sewer system, and be provided to the director of engineering or building official on request; redevelopment of a previously developed tract only triggers the requirement if it converts more than an acre from porous to impervious surface.

Smaller sites, under one acre and not part of a bigger development, instead need a city erosion control plan for commercial, industrial, multi-family or subdivision construction. Sec. 26-327 spells out the actual pollution control measures a 'responsible party,' meaning the owner, developer, builder or general contractor with operational control of the site, must implement and maintain: silt fences, straw bales or vegetative buffer strips to slow runoff, stabilized construction entrances to stop soil from being tracked onto streets, inlet protection barriers, dust control, waterproof storage for chemicals and paints, and a ban on washing out concrete trucks anywhere that lets wash water reach the storm sewer system.

The responsible party must inspect all pollution controls every 14 days and within 24 hours of a rainfall of half an inch or more, and a certificate of occupancy cannot issue until the building official confirms every temporary and permanent measure in the plan is complete.

Violations & Fines

A construction site's responsible party (the owner, developer, builder or contractor with operational control) who fails to implement or maintain the required erosion and pollution controls under Sec. 26-327 can be held up at the finish line: the building official will not issue a certificate of occupancy, and the director of engineering will not accept required improvements, until every temporary and permanent control in the plan is verified complete. Tracking soil off-site, discharging concrete washout into the storm sewer, or failing to inspect controls every 14 days are all specifically cited violations of the pollution control measures.

Frequently Asked Questions

Do I need an erosion control plan to build a house in Waco?
If your lot is part of a larger residential subdivision, the developer's stormwater pollution prevention plan generally covers it, but single-lot construction under an acre and not part of a larger development still needs the erosion control plan required under Sec. 26-326(h) for subdivisions, multifamily, commercial and industrial construction.
What erosion control measures does Waco actually require during construction?
Sec. 26-327 lists silt fences, straw bales, vegetative buffer strips, stabilized construction entrances, inlet protection barriers, dust control and sealed storage for chemicals and paints, plus a ban on discharging concrete truck washout into the storm sewer system, streets or waterways.
How often do erosion controls have to be inspected on a Waco job site?
The responsible party must inspect all pollution control measures every 14 days, and again within 24 hours after any rainfall of half an inch or more, keeping a record of each inspection as part of the stormwater pollution prevention plan.

Sources & Official References

Other rules in Waco

All Waco rules

Texas rules heatmap·Compare Waco to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Waco, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.