Waco, TX Environmental Rules: Erosion Control (2026)
Key Facts
- SWPPP trigger
- Sites disturbing 1 acre or more, or part of larger project
- Smaller-site plan
- Erosion control plan required under 1 acre for most uses
- Inspection frequency
- Every 14 days, and within 24 hrs of 0.5in rain
- C.O. hold
- No certificate of occupancy until controls are complete
- Responsible party
- Owner, developer, builder or general contractor in control
Summary
Waco requires anyone disturbing an acre or more, or a smaller site inside a larger development, to file a stormwater pollution prevention plan and run erosion controls like silt fences, straw bales and stabilized entrances while building. Sites under an acre and outside a larger project still need a city erosion control plan for commercial, industrial, multifamily or subdivision work.
(a)The responsible party of any construction site within the city shall implement measures necessary to control erosion, sedimentation, debris, and stormwater pollution. The responsible party is responsible for the maintenance and performance of the temporary pollution control measures until permanent measures are in place. The pollution controls are designed to be selected by the developer based on the most cost effective and appropriate means to provide the required controls.(b)Temporary pollution control measures (during construction)...(1)Structural control of soil erosion.a.Stilt fences may be utilized, where necessary, to retain the sediments from disturbed areas within the site and decrease the velocity of sheet flows...c.Stabilized construction entrances shall be designed to reduce the amount of soil tracked off the construction site by vehicles leaving the site.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 88).
Full Breakdown
Chapter 26's stormwater article requires a site-specific stormwater pollution prevention plan (SWPPP) for any residential, commercial or industrial development that disturbs one acre or more, or a smaller parcel that is part of a larger common plan of development, under Sec. 26-326. That SWPPP must satisfy EPA or TCEQ construction general permit rules, identify the outfall into the city's storm sewer system, and be provided to the director of engineering or building official on request; redevelopment of a previously developed tract only triggers the requirement if it converts more than an acre from porous to impervious surface.
Smaller sites, under one acre and not part of a bigger development, instead need a city erosion control plan for commercial, industrial, multi-family or subdivision construction. Sec. 26-327 spells out the actual pollution control measures a 'responsible party,' meaning the owner, developer, builder or general contractor with operational control of the site, must implement and maintain: silt fences, straw bales or vegetative buffer strips to slow runoff, stabilized construction entrances to stop soil from being tracked onto streets, inlet protection barriers, dust control, waterproof storage for chemicals and paints, and a ban on washing out concrete trucks anywhere that lets wash water reach the storm sewer system.
The responsible party must inspect all pollution controls every 14 days and within 24 hours of a rainfall of half an inch or more, and a certificate of occupancy cannot issue until the building official confirms every temporary and permanent measure in the plan is complete.
Violations & Fines
A construction site's responsible party (the owner, developer, builder or contractor with operational control) who fails to implement or maintain the required erosion and pollution controls under Sec. 26-327 can be held up at the finish line: the building official will not issue a certificate of occupancy, and the director of engineering will not accept required improvements, until every temporary and permanent control in the plan is verified complete. Tracking soil off-site, discharging concrete washout into the storm sewer, or failing to inspect controls every 14 days are all specifically cited violations of the pollution control measures.
Frequently Asked Questions
Do I need an erosion control plan to build a house in Waco?
What erosion control measures does Waco actually require during construction?
How often do erosion controls have to be inspected on a Waco job site?
Sources & Official References
Other rules in Waco
Texas rules heatmap·Compare Waco to another location·View the Texas environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.