Walton County, FL Environmental Rules: Erosion Control (2026)
Key Facts
- Protection zone width
- 300 feet landward of the lake
- Required controls
- hay bales, siltation barriers, filter berms
- Controls stay until
- permanent vegetation is stabilized
- Governing section
- LDC § 4.02.03.B
- Amendment threshold
- 4 of 5 commissioners must approve
Summary
Any construction within 300 feet of one of Walton County's coastal dune lakes, the rare water bodies that give South Walton's 30A corridor its name, must keep erosion controls such as staked hay bales, siltation barriers and floating silt or filter berms in place under LDC § 4.02.03 until permanent vegetation stabilizes the disturbed ground.
The Coastal Dune Lake Protection Zone is defined as being all lands within an area beginning at the mean or ordinary high water line of the Coastal Dune Lakes and their tributaries and extending 300 feet landward. ... B.Erosion control: Specific erosion control measures shall be utilized during construction activity, such as staked and staggered hay bales, siltation barriers, floating silt and filter berms. Further, erosion and sedimentation controls shall be left in place until the disturbed areas are stabilized with permanent vegetation that will prevent the transport of sediment off site.
Full Breakdown
The Coastal Dune Lake Protection Zone (CDLPZ) extends 300 feet landward from the mean or ordinary high water line of the county's coastal dune lakes and their tributaries. B is the specific erosion-control mandate within that zone: builders must use "staked and staggered hay bales, siltation barriers, floating silt and filter berms" during construction, and those measures must stay in place until the disturbed soil is stabilized by permanent vegetation that stops sediment from leaving the site. The same section pairs erosion control with a certified Low Impact Development stormwater plan (Subsection A), a ban on new septic systems where central sewer is available (Subsection E), a requirement that at least 60 percent of the 300-foot zone stay pervious open space (Subsection F), and a mandatory county land-clearing permit before any clearing occurs within the CDLPZ (Subsection I).
03 carries an unusual supermajority lock: it "shall not be amended or repealed unless by an affirmative vote of at least four (4) members of the Board of County Commissioners," a higher bar than an ordinary ordinance change. c for the separate Shoreline Protection Zone around rivers, creeks and Choctawhatchee Bay, so a project touching both a dune lake and a bay shoreline must satisfy each zone's own clause.
Violations & Fines
Clearing or building within the Coastal Dune Lake Protection Zone without the erosion controls required by § 4.02.03.B, or without the land-clearing permit required by § 4.02.03.I, is enforced under LDC Chapter VII: the code officer must require any breached sediment control to be repaired within 24 hours, and a Code Enforcement Officer can otherwise issue a citation carrying a civil fine of up to $500 per violation before the Code Compliance Special Magistrate.
Frequently Asked Questions
How close to a coastal dune lake can construction happen in Walton County?
What erosion controls does the county require during construction near a dune lake?
How hard is it to change the dune-lake erosion-control rule?
Sources & Official References
Other rules in Walton County
Florida rules heatmap·Compare Walton County to another location·View the Florida environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.