West Palm Beach, FL Environmental Rules: Erosion Control (2026)
Key Facts
- Governing section
- City Code § 94-316(d)
- Land-disturbance trigger
- 4,500 sq ft or more
- Excavation/fill trigger
- 400 cubic yards or more
- Utility trench trigger
- 300 feet of pipe/utility work
- Required document
- City-approved SWPPP before starting
- Financial assurance
- Erosion control + land stabilization bonds
- Permit revocation
- After two written warnings
Summary
West Palm Beach requires a city-approved stormwater pollution prevention plan before breaking ground on any subdivision, new building, or land-disturbing project affecting 4,500 square feet or more, under City Code § 94-316(d)(3). Contractors must also post an erosion control bond and keep sediment controls in place for the entire construction period.
3. Erosion control measures . a. Applicability. Erosion control measures are required for the following sites of land disturbing construction or land development activities: ... Sites involving grading, removing of protective ground cover or vegetation, excavating, land-filling or other land disturbing activities affecting a surface area of 4,500 square feet or more. Sites involving excavating or land-filling or a combination of excavating and filling affecting 400 cubic yards or more of dirt, sand or other excavation or fill material. ... Those sites involving the laying, repairing, replacing or enlarging of an underground pipe, utility main or similar facility for a distance of 300 feet or more. b. All sites for which erosion control measures are required, described in subsection (a) immediately above, shall comply with the city's stormwater management program and shall submit a stormwater pollution prevention plan (SWPPP) for approval by city.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 76).
Full Breakdown
Section 94-316 of the zoning code, 'Vacant lot and construction site maintenance,' requires erosion control measures on any site with a filed plat for houses, duplexes, condominiums, townhouses or apartments; commercial, industrial or institutional construction; grading or excavation disturbing 4,500 square feet or more; excavation or fill of 400 cubic yards or more; street, highway, road or bridge work; and underground pipe or utility installation running 300 feet or more, per § 94-316(d)(3)(a). Every covered site must comply with the city's stormwater management program and submit a stormwater pollution prevention plan (SWPPP) for approval before the engineering services director signs off, and it is unlawful to begin construction activity before the SWPPP is approved and a building, demolition, or right-of-way permit is issued, per § 94-316(c)(1).
The approved SWPPP must be maintained in a satisfactory manner for the entire construction period, and every erosion control measure installed under it must be removed once the work is done, § 94-316(d)(3)(c). If a building or demolition permit expires, the site must be brought to grade, tilled, and planted with irrigated ground cover within 30 days, § 94-316(d)(3)(d). The engineering services director may waive stormwater program or SWPPP requirements case by case for sites under one acre or individual single-family lots in an already-platted subdivision, § 94-316(d)(4).
Contractors, subcontractors, and permit applicants must also post an erosion control bond and a separate land stabilization bond, in amounts set by city resolution, to cover the cost of finishing erosion control and stabilization if the permit lapses; neither bond is required for a single-family home, duplex, or accessory apartment and its additions or renovations, § 94-316(e)(1)-(2).
Violations & Fines
Starting land-disturbing work before the engineering services director approves the SWPPP, or before a building, demolition, or right-of-way permit issues, is unlawful under § 94-316(c)(1). The development services director can revoke a building or demolition permit after two prior written warnings for violating the site-maintenance or erosion control standards, § 94-316(c)(4), and an expired permit lets the city draw on the posted erosion control and land stabilization bonds to cover cleanup costs.
Frequently Asked Questions
When does West Palm Beach require an erosion control plan?
Can I start grading before my SWPPP is approved?
Do small single-family projects need an erosion control bond?
What happens if my building permit expires before erosion control is finished?
Sources & Official References
Other rules in West Palm Beach
Florida rules heatmap·Compare West Palm Beach to another location·View the Florida environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.