Denver, CO Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Freeboard required
1.5 ft above BFE
Critical facilities
2 ft freeboard or dry floodproof
Proof required
FEMA Elevation Certificate
Enforcing agency
Denver floodplain administrator
Max civil penalty
$999 per day

Summary

Denver requires new and substantially improved residential structures in the flood storage area to elevate their lowest floor, including any basement, at least one and one-half feet above the base flood elevation.

Have the lowest floor (including basement) and all associated machinery and equipment, elevated with a minimum of one and one-half (1½) feet of freeboard.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 147 Update 3).

Full Breakdown

Denver Revised Municipal Code § 56-203(e)(1) requires new construction, additions, and substantial improvements to residential structures within the regulatory floodplain's flood storage area to have the lowest floor, including any basement, plus all machinery and equipment, elevated at least one and one-half feet above the base flood elevation (freeboard). Nonresidential buildings must meet the same 1.5-foot freeboard or dry floodproof to that height, and critical facilities need two feet of freeboard or dry floodproofing. Owners must submit a FEMA Elevation Certificate to the floodplain administrator before the city issues a certificate of occupancy.

Violations & Fines

Failing to correct a floodplain violation draws a civil penalty of up to $999 per day under D.R.M.C. § 56-205, plus possible liens and injunctive action by the city.

Frequently Asked Questions

How much freeboard does Denver require above base flood elevation?
Residential and most nonresidential structures in Denver's flood storage area need the lowest floor at least 1.5 feet above BFE; critical facilities need 2 feet.
What happens if a Denver flood-zone structure isn't elevated correctly?
The floodplain administrator can order corrections, and noncompliance can bring a civil penalty of up to $999 per day under § 56-205.

Sources & Official References

Other rules in Denver

All Denver rules

Compare Denver to another location·View the Colorado environmental rules overview

Get notified when Flood Elevation Requirements in Denver, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.