Skip to main content
CityRuleLookup

Houston, TX Environmental Rules: Flood Elevation Requirements (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Standard
500-year elevation + 2 feet
Governing code
Code of Ordinances Ch. 19
Effective
Sept 1, 2018 (post-Harvey)
Critical facilities
3 feet above 500-year level
Enforcer
City engineer, Houston Public Works

Summary

In Houston's 0.2% annual chance (500-year) floodplain, new homes and substantial improvements must sit at the minimum flood protection elevation: the 500-year flood elevation plus two feet. The Hurricane Harvey-driven rule took effect September 1, 2018.

Minimum flood protection elevation means the 0.2 percent flood elevation, plus 2 feet. ... (b) The following additional requirements apply in an X Shaded Zone: (1) Any addition to, and new construction of any residential structure shall: a. Have the lowest floor and all utilities elevated to at least the minimum flood protection elevation ...; (2) Any addition to, and new construction of nonresidential structure: a. Shall be elevated to at least the minimum flood protection elevation measured to the lowest floor; or b. Shall ... be floodproofed to the minimum flood protection elevation.

Full Breakdown

Chapter 19 defines the 'minimum flood protection elevation' as the 0.2 percent flood elevation plus 2 feet (Sec. 19-2). Section 19-33(b) applies this to the X Shaded Zone: the 500-year floodplain: any new residential structure must have its lowest floor and all utilities elevated to at least that height, and new nonresidential buildings must be elevated or floodproofed to it. Critical facilities must reach 3 feet above the 500-year elevation (Sec. 19-33(e)). The city engineer at Houston Public Works issues the required floodplain development permit, and the 2018 amendments also extended the zero-net-fill rule to the 500-year floodplain.

Violations & Fines

Construction below the minimum flood protection elevation is denied a floodplain development permit; the city engineer can revoke an issued permit under Sec. 19-23 and halt work until the structure meets Chapter 19 elevation standards.

Frequently Asked Questions

Does the 2-foot rule apply outside the FEMA 100-year floodplain?
Yes. Houston applies the minimum flood protection elevation across the X Shaded Zone, the 0.2% annual chance (500-year) floodplain, not just the 100-year special flood hazard area.
Can a nonresidential building be floodproofed instead of elevated?
Yes. Under Sec. 19-33(b)(2), a new nonresidential structure in the 500-year floodplain may be floodproofed, along with its sanitary sewerage facilities, to the minimum flood protection elevation rather than elevated.
When did Houston change this elevation requirement?
City Council adopted the amendments on April 4, 2018 (Ord. No. 2018-258), and they took effect September 1, 2018, in response to Hurricane Harvey flooding.

Sources & Official References

Other rules in Houston

All Houston rules

Texas rules heatmap·Compare Houston to another location·View the Texas environmental rules overview

Get notified when Flood Elevation Requirements in Houston, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Harris County handle flood elevation requirements.

Baytown, TX
Some Restrictions