Skip to main content
CityRuleLookup

Polk County, IA Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Residential lowest floor
min. 1 foot above BFE
Compacted fill extension
at least 18 feet beyond structure
Levee/flood wall freeboard
min. 3 feet above BFE
Mobile homes
1 foot above BFE, permanent foundation
Utility/sanitary systems
1 foot above BFE protection
Certification required
Iowa-registered professional engineer

Summary

New or substantially improved homes in the unincorporated Polk County floodplain must have the lowest floor at least one foot above the 1% Annual Chance base flood elevation, built on compacted fill extending 18 feet beyond the structure. Levees and flood walls must carry three feet of design freeboard on top of that same base flood elevation.

City-specific rules exist: Des Moines has its own flood elevation requirements rules that differ from Polk County's county-level regulations. If you live in Des Moines, check the city-specific page instead.

All residential structures which are constructed or substantially improved after the date of adoption of this Ordinance shall have the lowest floor, including lowest level, elevated a minimum of one (1) foot above the 1% Annual Chance flood level. Construction shall be upon compacted fill which shall, at all points, be no lower than one (1) foot above the 1% Annual Chance flood level and extend at such elevation at least eighteen (18) feet beyond the limits of any structure erected thereon. ... Structures such as levees, flood walls, etc. which provide protection from a 1% Annual Chance flood shall have a minimum of three (3) feet of design freeboard and shall provide for adequate interior drainage. ... Base Flood Elevation (BFE). The elevation floodwaters would reach at a particular site during the occurrence of a base flood event.

View official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

Article 7, Section 1(J) of the Polk County Zoning Ordinance sets the county's freeboard standard against the 'Base Flood Elevation,' defined in Section 1(Q) as the elevation floodwaters would reach at a site during a base flood, the flood with a 1 percent chance of occurring in any given year. Under Section 1(J)(1)(c), residential structures built or substantially improved after the ordinance's adoption must have the lowest floor, including the lowest level, elevated a minimum of one foot above the 1% Annual Chance flood level, built on compacted fill that stays at or above that one-foot elevation and extends at least 18 feet beyond the structure.

Nonresidential structures get the same one-foot minimum on the first floor, or must be floodproofed to that level instead. The same one-foot-above-BFE floor applies to new mobile homes on permanent foundations and to wastewater and water supply treatment facilities. Structural flood control works are held to a stricter standard: levees, flood walls and similar structures that are meant to protect against the 1% Annual Chance flood must carry a minimum of three feet of design freeboard above base flood elevation and provide adequate interior drainage, and any such structural flood control work needs Department of Natural Resources approval when required.

All of this construction must be certified by a professional engineer registered in Iowa as meeting these conditions before a Floodplain Development Permit is finalized.

Violations & Fines

Constructing or substantially improving a structure below the required one-foot elevation above base flood elevation, or building a flood control structure without the required three feet of freeboard, violates Article 7, Section 1(J) and is enforced under Article 23. The Zoning Administrator serves written notice with a correction deadline of up to 30 days, each additional day is a separate violation, and the county can assess a daily civil penalty, issue a stop-work order, and place a lien to recover abatement costs.

Frequently Asked Questions

How high above the flood level must a new house be built in unincorporated Polk County?
Section 1(J)(1)(c) of the Zoning Ordinance requires the lowest floor, including any basement level, to sit at least one foot above the 1% Annual Chance base flood elevation, built on compacted fill that extends at least 18 feet beyond the structure at that elevation or higher.
What is base flood elevation?
Section 1(Q) defines Base Flood Elevation, or BFE, as the elevation floodwaters would reach at a particular site during a base flood, meaning the flood that has a 1 percent chance of being equaled or exceeded in any given year, also called the 100-year flood.
Do levees need extra freeboard beyond the base flood elevation?
Yes. Section 1(J)(6) requires levees, flood walls and similar flood control structures to carry a minimum of three feet of design freeboard above the base flood elevation, plus adequate interior drainage, and Department of Natural Resources approval when required.
Are mobile homes held to the same elevation standard as houses?
Yes. Section 1(J)(9) requires new and substantially improved factory-built and mobile homes to be elevated on a permanent foundation so the lowest floor sits at least one foot above the base flood elevation, and anchored to resist flotation and lateral movement.

Sources & Official References

Other rules in Polk County

All Polk County rules

Compare Polk County to another location·View the Iowa environmental rules overview

Get notified when Flood Elevation Requirements in Polk County, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Cities Across Polk County