FEMA flood zone rules in Elyria, OH, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.

Key Facts

Permit issued by
City Engineer, the Floodplain Administrator
Review deadline
Thirty days after a complete application
Permit expiry
One year after issuance unless substantially begun
Exempt work
Maintenance and nonstructural work under $5,000, excluding fill and grading
Fine
Minimum $100 per offense, each day separate
Maps on file
Engineering Department, 131 Court Street

Summary

In the City of Elyria, Ohio, Section 1386.14 makes it unlawful to begin construction, filling, grading or any other development in an identified special flood hazard area until a floodplain development permit is obtained. The City Engineer, as Floodplain Administrator, approves or disapproves within thirty days of a complete application.

It shall be unlawful for any person to begin construction or other development activity including, but not limited to filling; grading; construction; alteration, remodeling, or expanding any structure; or alteration of any watercourse wholly within, partially within or in contact with any identified special flood hazard area, as established in Section 1386.06, until a floodplain development permit is obtained. Such floodplain development permit shall show that the proposed development activity is in conformity with the provisions of these regulations. No such permit shall be issued by the Floodplain Administrator until the requirements of these regulations have been met.

Full Breakdown

Chapter 1386 covers the special flood hazard areas along the Black River and elsewhere in the City. Section 1386.06 adopts the Flood Insurance Study and Flood Insurance Rate Map for Lorain County, Ohio and Incorporated Areas, both effective August 19, 2008, and the maps are on file in the Engineering Department at Elyria City Hall, 131 Court Street. Section 1386.14 then makes a floodplain development permit mandatory for filling, grading, construction, alteration, remodeling or expanding any structure, and alteration of any watercourse, wholly within, partially within or in contact with an identified special flood hazard area.

The City Engineer is the Floodplain Administrator (Section 1386.12). The owner or an authorized agent applies before work starts, with site plans drawn to scale, the elevation of the existing natural ground where structures are proposed, and the elevation of the lowest floor, including basement, of all proposed structures (Section 1386.15). Engineering certifications are added when they apply, such as floodproofing certification for non-residential structures. Within thirty days after receiving a complete application, the Floodplain Administrator approves or disapproves it, and a permit expires one year after issuance unless the activity has been substantially begun and is pursued to completion (Section 1386.16). The Administrator makes periodic inspections during construction (Section 1386.17), and after construction an FEMA Elevation Certificate completed by a registered surveyor records as-built elevations for new or substantially improved residential structures (Section 1386.18).

Exemptions are narrow. No application is needed for maintenance work such as roofing, painting and basement sealing, or for small nonstructural development valued at less than five thousand dollars ($5,000), and that dollar exemption never covers filling and grading (Section 1386.20). Section 1386.25(b) prohibits private water supply systems permitted under Ohio R.C. Chapter 3701, infectious waste treatment facilities, storage or processing of hazardous, flammable, radioactive, explosive or water reactive materials, and storage of material that could become buoyant in floodway areas.

Violations & Fines

Failure to obtain a floodplain development permit is a violation under Section 1386.42(b). Section 1386.44 makes it a strict liability offense and a minor misdemeanor with a minimum fine of one hundred dollars ($100.00) per offense, and each day the violation continues is a separate offense. The Floodplain Administrator issues a written notice of violation under Section 1386.43 with a reasonable time for performance, and a revoked permit can be appealed to the Appeals Board.

Frequently Asked Questions

Do I need a permit to build in an Elyria flood zone?
Yes. Section 1386.14 makes it unlawful to begin construction or other development, including filling, grading, remodeling, expanding a structure or altering a watercourse, wholly within, partially within or in contact with an identified special flood hazard area until a floodplain development permit is obtained from the Floodplain Administrator.
Who issues floodplain permits in Elyria and how fast?
The City Engineer serves as Floodplain Administrator under Section 1386.12. Under Section 1386.16, the Administrator approves or disapproves a complete application within thirty days. Permits are conditional on starting work within one year, and a permit expires one year after issuance unless the activity has been substantially begun and is pursued to completion.
Which projects are exempt from the floodplain permit in Elyria?
Section 1386.20 exempts maintenance work such as roofing, painting and basement sealing, and small nonstructural development valued at less than $5,000, though filling and grading are not covered by that exemption. It also exempts certain manufactured home park work under state authority and facilities permitted by state siting boards.
What is the penalty for building in a flood zone without a permit in Elyria?
Section 1386.42(b) makes failure to obtain a permit a violation, punishable under Section 1386.44. That section sets a strict liability minor misdemeanor with a minimum fine of $100.00 per offense, and each day the violation continues is a separate offense. The City can also take other lawful action to prevent or remedy the violation.

Sources & Official References

Other rules in Elyria

All Elyria rules

Compare Elyria to another location·View the Ohio environmental rules overview

Get notified when Flood Zones in Elyria, OH changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.