FEMA flood zone rules in Floyd County, IN, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Waterway buffer
- 25 ft beyond FEMA flood plain, or 50 ft from bank
- No-disturbance buffer
- 25 ft from top of waterway bank
- Applies to
- Waterways draining 25+ acres or blue-line streams
- Restriction
- No building or structure in buffer
- Enforcing office
- Floyd County Stormwater Management
Summary
Floyd County's post-construction stormwater ordinance bars new buildings and structures within a waterway buffer measured from the FEMA-mapped flood plain boundary, on top of a separate 25-foot no-disturbance buffer along waterway banks.
(2) The waterway buffer will be used to define areas where land disturbance activities shall be permitted, but construction of any building or structure shall not be permitted. ... (c) The waterway buffer shall be define as the area contained within a boundary established 25 feet beyond the flood plain boundary, as defined by FEMA, or 50 feet from top of waterway bank, as defined by geomorphic shape (not by the current water surface elevation), whichever is larger.
Full Breakdown
046(B) of the Floyd County Code requires every post-construction Stormwater Pollution Prevention Plan (SWPPP) to include buffer provisions tied to the FEMA flood plain. 046(B)(2), a waterway buffer defines an area where land-disturbing activity is allowed but construction of any building or structure is not permitted. 046(B)(2)(c) fixes that buffer as the area within a boundary set 25 feet beyond the FEMA-mapped flood plain boundary, or 50 feet from the top of the waterway bank measured by geomorphic shape rather than current water level, whichever distance is larger.
046(B)(2)(a). Automatic exemptions exist for roads and utilities crossing waterways and for pedestrian trails and walkways near waterways, provided erosion, sediment and water-quality controls are addressed. 046(B)(1), where grading, clearing and grubbing are barred outright, though pruning and partial vegetation removal are allowed. The waterway buffer must be at least as wide as the no-disturbance buffer where both apply, and the buffer area may still host water-quality devices if erosion and sediment controls are satisfied, as determined by the county. This chapter is administered by Floyd County Stormwater Management under Ordinance 2019-25.
Violations & Fines
Building within the mapped waterway buffer without county approval is enforced through Chapter 152's stormwater permitting and penalty framework: violations tied to post-construction requirements under Sections 152.025 through 152.032 carry a civil penalty of not more than $2,500 per offense under Section 152.999(B), and unresolved buffer violations can also be treated as a public nuisance subject to injunctive relief.
Frequently Asked Questions
Can I build within the floodplain buffer in unincorporated Floyd County?
How is the Floyd County waterway buffer measured?
Are any activities exempt from the Floyd County waterway buffer?
Sources & Official References
Other rules in Floyd County
Compare Floyd County to another location·View the Indiana environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.