Howard County, MD Environmental Rules: Flood Zones (2026)
FEMA flood zone rules in Howard County, MD, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Permit required for
- filling, grading, new construction, manufactured homes
- Permit validity
- 180 days to start work
- Extension length
- up to 90 days, written request
- Floodway standard
- no more than 1 ft rise
- Administered by
- Director of Public Works (Floodplain Administrator)
- FIRM effective date
- November 6, 2013
Summary
No one may fill, grade, build, or place a manufactured home within, partially within, or touching a special flood hazard area in Howard County without a permit. County Code Section 16.706 routes every such project through the Floodplain Administrator, the Director of Public Works, and requires construction to start within 180 days of permit issuance.
(a)Permits Required. A person shall not begin any development or construction which is wholly within, partially within, or in contact with any flood hazard area established in section 16.703 of this subtitle, including but not limited to: Filling; grading; construction of new structures; the substantial improvement of buildings or structures, including repair of substantial damage; placement or replacement of manufactured homes, including substantial improvement or repair of substantial damage of manufactured homes; erecting or installing a temporary structure, or alteration of a watercourse, until a permit is obtained from the County in accordance with the requirements of this subtitle and the Howard County Building Code.(c)A Permit is Valid Provided the Actual Start of Work is Within 180 Days of the Date of Permit Issuance. Requests for extensions shall be submitted in writing and justifiable cause demonstrated. The Floodplain Administrator may grant, in writing, one or more extensions of time, for additional periods not exceeding more than 90 days each...
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 91 | Zoning: Supplement 25).
Full Breakdown
Howard County's floodplain management subtitle, Title 16, Subtitle 7, treats the special flood hazard area shown on FEMA's Flood Insurance Rate Maps for the county, effective November 6, 2013, and any later revisions, as off-limits to unpermitted work. Section 16.706(a) requires a permit before a person begins any development or construction wholly within, partially within, or in contact with a flood hazard area established under Section 16.703, and it lists filling, grading, construction of new structures, substantial improvement of an existing building including repair of substantial damage, placement or replacement of a manufactured home, erecting a temporary structure, and altering a watercourse as covered activities.
The Director of Public Works, acting as Floodplain Administrator under Section 16.708, reviews each application to confirm the work will be reasonably safe from flooding and that all required federal, state, and local approvals, including any Maryland Department of the Environment nontidal-waters permit, have been obtained. Once issued, a permit is valid only if the applicant actually starts work within 180 days; Section 16.706(c) lets the Floodplain Administrator grant one or more written extensions of up to 90 days each, but only if the flood hazard area and base flood elevation data used to issue the permit has not since been amended or revised.
The floodplain itself is split into three parts under Section 16.702: the floodway, which must carry the one-percent annual chance flood without raising the water surface more than one foot; the floodway fringe; and the approximate floodplain, where the boundary has not been surveyed in detail. Recreational vehicles cannot be parked or stored in a special flood hazard area at all under Section 16.705(d), and new water and sewer systems built in the floodplain must be designed to minimize floodwater infiltration under Section 16.705(e).
Violations & Fines
Building, filling, grading, or placing a manufactured home in a special flood hazard area without a Section 16.706 permit is a violation the Floodplain Administrator can act on directly: the Administrator can issue a notice of violation or a stop-work order and require corrective action, and Section 16.707 makes clear the county's review does not shift liability for flood damage onto Howard County if a larger flood than planned for occurs.
Frequently Asked Questions
Do I need a permit to build in a Howard County flood zone?
How long is a Howard County floodplain permit good for?
Can I park my RV in a flood hazard area in Howard County?
Sources & Official References
Other rules in Howard County
Compare Howard County to another location·View the Maryland environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.