FEMA flood zone rules in Greenburgh, NY, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.

Key Facts

Permit administrator
Town Engineer
Application fee
$250
Possible review deposit
Up to $500
FIRM effective date
September 28, 2007
Chapter adopted
8-15-2007, L.L. No. 9-2007
Max penalty
$250 fine or 15 days jail per day

Summary

Greenburgh requires a floodplain development permit before any construction, filling, grading or excavation in an area of special flood hazard shown on the Town's FEMA Flood Insurance Rate Maps. The Town Engineer, acting as local administrator, reviews every application and can deny or condition approval to keep new development out of harm's way.

A floodplain development permit is hereby established for all construction and other development to be undertaken in areas of special flood hazard in this community for the purpose of protecting its citizens from increased flood hazards and ensuring that new development is constructed in a manner that minimizes its exposure to flooding. It shall be unlawful to undertake any development in an area of special flood hazard, as shown on the Flood Insurance Rate Map enumerated in § 220-3B, without a valid floodplain development permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4570580; v39 updated 2025-10-22; through 10-22-2025).

Full Breakdown

L. No. 9-2007 and covers all areas of special flood hazard identified on the Town's FEMA panels (Community Number 360911, FIRM effective September 28, 2007) plus later Letters of Map Revision for the Saw Mill River corridor. Section 220-4 designates the Town Engineer as local administrator and makes it unlawful to undertake development, including manufactured home and recreational vehicle parks, subdivisions and watercourse alterations, in a special flood hazard area without a valid floodplain development permit. Applications must show elevations, dimensions, drainage facilities and material storage, and must be accompanied by a $250 fee; the administrator may also require a deposit of up to $500 to cover extra review, inspection and approval costs.

Applicants for structures with basements or lowest floors in Zones A1-A30, AE or AH must submit as-built elevation certificates from a licensed engineer or surveyor once the lowest floor is complete, and nonresidential floodproofing requires a certified floodproofing elevation. The local administrator reviews for compliance with the construction standards in § 220-5, can require technical analyses showing a project will not damage neighboring property, notifies FEMA and the state DEC before any watercourse alteration, and issues stop-work orders for unpermitted or noncompliant work. Occupancy of any flood-hazard structure is unlawful until the administrator issues a certificate of compliance based on inspections and submitted elevation or floodproofing certificates.

Violations & Fines

Building without a permit, ignoring a stop-work order, or occupying a structure without a certificate of compliance is a violation of § 220-3D punishable by up to $250 per offense or 15 days' imprisonment, or both, with each day of noncompliance a separate offense. Noncompliant structures without an approved § 220-6 variance are reported to FEMA.

Frequently Asked Questions

Do I need a permit to build in a Greenburgh flood zone?
Yes. Section 220-4B makes it unlawful to undertake any development, including construction, filling or grading, in an area of special flood hazard shown on the Town's FEMA Flood Insurance Rate Map without a valid floodplain development permit issued by the Town Engineer.
How much does a Greenburgh floodplain permit cost?
The base application fee is $250. The local administrator can also require a deposit of no more than $500 to cover additional costs of reviewing, inspecting and approving the project before the permit is issued.
What happens if I build in a flood zone without a permit?
Section 220-3D makes unpermitted or noncompliant work a violation punishable by a fine of up to $250 or imprisonment up to 15 days, or both, with each day of continued noncompliance treated as a separate offense, and the structure reported to FEMA.

Sources & Official References

Other rules in Greenburgh

All Greenburgh rules

New York rules heatmap·Compare Greenburgh to another location·View the New York environmental rules overview

Get notified when Flood Zones in Greenburgh, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Zones in Nearby Cities

How other cities in Westchester County handle flood zones.

New Rochelle, NY
Some Restrictions
Mount Vernon, NY
Some Restrictions
Yonkers, NY
Significant Restrictions