Irondequoit, NY Environmental Rules: Flood Zones (2026)
FEMA flood zone rules in Irondequoit, NY, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Permit required
- Any development in an area of special flood hazard (§ 136-12)
- Application fee
- $25, plus reimbursement of added review costs
- Review deposit
- Local administrator can require no more than $500
- Local administrator
- Director of Community Development
- Maximum penalty
- $250 fine or 15 days in jail, or both
- Map effective date
- July 31, 2024 for several FIRM panels
Summary
In the Town of Irondequoit, New York, no one can undertake development in an area of special flood hazard without a valid floodplain development permit under Chapter 136. The application fee is $25, and the Director of Community Development, acting as local administrator, grants or denies every permit. A conviction carries a fine of no more than $250, up to 15 days in jail, or both.
A. Purpose. A floodplain development permit is hereby established for all construction and other development to be undertaken in areas of special flood hazard in this community for the purpose of protecting its citizens from increased flood hazards and insuring that new development is constructed in a manner that minimizes its exposure to flooding. It shall be unlawful to undertake any development in an area of special flood hazard, as shown on the Flood Insurance Rate Map enumerated in § 136-6, without a valid floodplain development permit. ... B. Fees. ... All applications for a floodplain development permit shall be accompanied by an application fee of $25. In addition, the applicant shall be responsible for reimbursing the Town of Irondequoit for any additional costs necessary for review, inspection and approval of this project, including, but not limited to, the legal fees incurred by the Town. The local administrator may require a deposit of no more than $500 to cover these additional costs.
Full Breakdown
Chapter 136 of the Town of Irondequoit Code applies to every area of special flood hazard inside the Town, in Monroe County. Section 136-6 maps those areas through FEMA Flood Insurance Rate Map panels for Community Number 360422, several with an effective date of July 31, 2024, plus a Flood Insurance Study of the same date. The maps and study are on file at the Department of Community Development in the Town Hall, 1280 Titus Avenue.
The Director of Community Development is the local administrator under § 136-11. Section 136-12 makes the permit mandatory for all construction and other development in a mapped area, and the application can require plans in duplicate, drawn to scale, showing the nature, location, dimensions and elevations of the site, structures, fill, stored materials and drainage facilities. Beyond the $25 fee, the applicant reimburses the Town for added review, inspection and approval costs, including legal fees, and the administrator can demand a deposit of no more than $500.
Section 136-13 asks for the proposed elevation of the top of the lowest floor, basement or cellar included, for any new or substantially improved structure, and an as-built elevation certified by a licensed professional engineer or surveyor once that floor is in. In Zone A with no base flood elevation data, the applicant supplies it for developments greater than either 50 lots or five acres. Altering a watercourse requires engineering computations showing equal or greater conveyance.
Under § 136-14 the administrator refuses a permit if the work would physically damage other property or fails the Article V construction standards, issues stop-work orders for development found without a permit, and withholds occupancy until a certificate of compliance issues. A substantial improvement means a cost that equals or exceeds 50% of the structure's market value before construction starts.
Violations & Fines
Section 136-9 bars any structure from being built, located, extended, converted or altered, and any land from being excavated or filled, in an area of special flood hazard without full compliance. On conviction, the fine is no more than $250, imprisonment is not more than 15 days, or both, and each day of noncompliance is a separate offense. Ignoring a stop-work order draws the same penalties. A structure with no approved variance under Article VI is declared noncompliant and reported to FEMA.
Frequently Asked Questions
Who issues floodplain development permits in the Town of Irondequoit?
How much does a floodplain development permit cost?
Can I move into a building after finishing work in a flood hazard area?
What counts as a substantial improvement under Chapter 136?
Sources & Official References
Other rules in Irondequoit
New York rules heatmap·Compare Irondequoit to another location·View the New York environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Zones in Nearby Cities
How other cities in Monroe County handle flood zones.