Lincoln County, SD Environmental Rules: Flood Zones (2026)
FEMA flood zone rules in Lincoln County, SD, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Governing section
- Lincoln County Code § 153.045
- Zones covered
- FEMA Zone A and AE
- Buffer distance
- 100 ft or 8 ft elevation from SFHA
- Permit expires if unstarted
- 1 year after issuance
- Abandonment expiration
- 180 days suspended/abandoned
Summary
Anyone developing in a flood hazard area of unincorporated Lincoln County, South Dakota needs a permit from the county Floodplain Administrator before starting work. The permit covers Zone A and AE on the FEMA flood map and any land within 100 feet of distance or eight feet of elevation of a special flood hazard area.
§ 153.045 REQUIRED. Any person who intends to conduct any development in a flood hazard area or buffer zone shall first make application to the Floodplain Administrator and shall obtain the required permit prior to the start of development. Permits are required for all proposed construction and other developments, including the placement of manufactured homes, within Zone A or AE on the community's FIRM and within 100 feet of distance or eight feet of elevation (whichever comes first) from a special flood hazard area.
Full Breakdown
Lincoln County Code § 153.045 requires anyone intending to conduct development in a flood hazard area or buffer zone to first apply to the Floodplain Administrator and obtain the permit before starting. Permits are required for all proposed construction and other development, including placement of manufactured homes, within Zone A or AE on the community's Flood Insurance Rate Map (FIRM), and within 100 feet of distance or eight feet of elevation, whichever comes first, from a special flood hazard area. The permit application under § 153.046 must identify and describe the development, give its legal description or address, state its intended use, and be accompanied by building plans, an elevation certificate, a scaled site plan and grading plans showing proposed elevations, plus a description of any watercourse alteration.
The Floodplain Administrator weighs twelve listed factors under § 153.046(C) before approving or denying the permit, including the danger to life and property from flooding or erosion, the safety of emergency vehicle access during a flood, the costs of providing governmental services during and after flooding, and volumetric calculations demonstrating compensatory storage for fill activities in the floodplain. Under § 153.048, a permit becomes invalid if development is not started within one year of issuance or is suspended or abandoned for 180 days, though the Floodplain Administrator may grant an extension of up to 180 additional days.
The Administrator may also suspend or revoke a permit under § 153.049 if it was issued in error, based on inaccurate information, or in violation of any county ordinance.
Violations & Fines
Lincoln County Code § 153.116 treats development without the required floodplain permit, or in violation of this chapter's terms, as a misdemeanor punishable under SDCL § 7-18A-2, with each day of continued violation a separate offense; the Floodplain Administrator can issue a stop-work order under § 153.115 and can prevent occupancy of a noncompliant structure under § 153.047(B).
Frequently Asked Questions
Do I need a permit to build in a flood zone in Lincoln County?
What must a floodplain permit application include?
How long is a Lincoln County floodplain permit valid?
Sources & Official References
Other rules in Lincoln County
Compare Lincoln County to another location·View the South Dakota environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.