Ames, IA Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger threshold
1 acre disturbed, or 10,000 sq ft impervious cover
Redevelopment threshold
1 acre or more of new impervious cover
Design standard
Iowa Stormwater Management Manual sizing criteria
First violation penalty
$500 municipal infraction
Repeat violation penalty
$750 municipal infraction
Occupancy hold
Permits withheld until BMPs pass inspection
Appeal deadline
20 days, written, to City Council

Summary

In the City of Ames, Iowa, Chapter 5B of the Municipal Code requires any new development disturbing one acre or more of land, or creating over 10,000 square feet of impervious cover, to meet City stormwater management standards before a development or redevelopment application is approved. Violations are a municipal infraction carrying a $500 fine for a first offense and $750 for repeats, and occupancy permits are held until stormwater controls pass inspection.

Sec. 5B.1. GENERAL PROVISIONS ... (8) ... (a) City stormwater requirements must be met for a development application to be approved. City stormwater requirements apply to any new development disturbing one (1) acre or more of land or to any development disturbing less than said acreage of land if the amount of impervious cover created exceeds 10,000 square feet. ... (b) City stormwater requirements must be met for a redevelopment application to be approved. City stormwater requirements apply to redevelopment creating one (1) acre or more of impervious cover. ... Sec 5B.8. ENFORCEMENT BY LEGAL OR ADMINISTRATIVE ACTION ... (2) A violation of any provision of Chapter 5B shall be a municipal infraction punishable by a penalty of $500 for a person’s first violation thereof, and a penalty of $750 for each repeat violation. ... (4) Holds on Occupation Permits: Occupancy permits shall not be granted until all storm water management BMPs have been inspected and approved by City.

Full Breakdown

Ames adopted Chapter 5B to satisfy its Municipal Separate Storm Sewer System (MS4) permit from the Iowa Department of Natural Resources, requiring a program that controls stormwater runoff, erosion and non-point pollution from new construction and redevelopment (Sec. 5B.1(1)-(5)). The City adopts the Iowa Stormwater Management Manual's sizing criteria, design specifications and best management practices as its own standards (Sec. 5B.1(6)). Coverage is triggered by size: a new development application must meet City stormwater requirements if it disturbs one acre or more of land, or disturbs less land but creates more than 10,000 square feet of impervious cover; a redevelopment application is covered once it creates one acre or more of impervious cover (Sec.

5B.1(8)(a)-(b)). Exemptions cover agricultural activity and additions or modifications to an existing single-family property, and stricter water-quality treatment applies within 1,000 feet of the City's Southeast Well Field and Youth Sports Complex Well Field drinking-water wells. The ordinance is meant to work alongside Chapter 5A erosion control, Chapter 23 Subdivisions, Chapter 28 Utilities and Chapter 29 Zoning, and the stricter of any overlapping requirement controls (Sec. 5B.1(9)). Owners must maintain installed BMPs, keep at least three years of maintenance records, and submit to annual inspections (Sec.

5B.7). Enforcement under Sec. 5B.8 allows civil action with recovery of the City's attorneys' fees, or treats a violation as a municipal infraction punishable by $500 for a first violation and $750 for each repeat violation; the City can also require restoration of disturbed land and place unpaid costs as a lien on the property. Occupancy permits are withheld until all stormwater BMPs are inspected and approved, and decisions may be appealed to the City Council in writing within 20 days (Sec. 5B.8-5B.9).

Violations & Fines

A Chapter 5B violation is a municipal infraction: $500 for a first offense, $750 for each repeat offense, and the City can also sue civilly and recover its attorneys' fees (Sec. 5B.8). Violators may be ordered to restore disturbed land, and unpaid repair or restoration costs become a lien on the property. Occupancy permits are withheld until required stormwater BMPs are inspected and approved by the City.

Frequently Asked Questions

What size project needs a stormwater permit in Ames?
Sec. 5B.1(8)(a) covers any new development disturbing one acre or more of land, or a smaller site if it creates more than 10,000 square feet of impervious cover. Redevelopment projects are covered once they create one acre or more of impervious cover under Sec. 5B.1(8)(b).
Are there exemptions from Ames's stormwater rules?
Yes. Agricultural activity and additions or modifications to an existing single-family property are exempt under Sec. 5B.1(8)(a). Sites within 1,000 feet of the Southeast Well Field or Youth Sports Complex Well Field instead face added water-quality treatment requirements set by the Director of Public Works and Director of Water and Pollution Control.
What happens if my stormwater BMPs fail inspection?
Sec. 5B.7 lets the City require repair after notice, and if the BMP threatens public health or safety the responsible party gets 30 days to fix it before the City can do the work itself and place the cost as a lien on the property or the tax bill.
Can the City withhold my occupancy permit over stormwater issues?
Yes. Sec. 5B.8(4) states occupancy permits shall not be granted until all stormwater management BMPs have been inspected and approved by the City, on top of the $500 first-offense and $750 repeat-offense municipal infraction penalties for violations.

Sources & Official References

Other rules in Ames

All Ames rules

Compare Ames to another location·View the Iowa environmental rules overview

Get notified when Stormwater Management in Ames, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.