Aurora, CO Environmental Rules: Stormwater Management (2026)
Key Facts
- Permitting utility
- Aurora Water
- Permits required
- utility permit + discharge permit
- Min. dedicated easement
- 16 feet, sized for 100-yr storm
- Plan approval validity
- one year from approval
- Governing law
- Aurora City Code Ch. 138, Art. VII
Summary
Aurora requires a storm drainage system utility permit and a stormwater quality discharge permit from Aurora Water before building drainage infrastructure or discharging into any public right-of-way or easement.
It shall be unlawful for any person to construct, install, place or attempt to construct, install or place any storm drainage system extension or related subsurface structure or facility within any public street, avenue, alley or other public way or to discharge into a public right-of-way or easement, without first having obtained a storm drainage system utility permit and stormwater quality discharge permit with Aurora Water. The permit shall provide for the dedication of all public storm drainage system improvements so constructed or installed to Aurora Water upon such terms and conditions as the general manager may determine.
(b) Application for a storm drainage system utility permit extension agreement and stormwater quality discharge permit shall be made to Aurora Water on forms provided by the general manager. The applicant shall provide all necessary technical information and data regarding the proposed storm drainage system improvements as may be required by the general manager.
(c) Following issuance of the storm drainage system utility permit extension agreement and stormwater quality discharge permit and prior to commencing construction or installation of any storm drainage system improvements, and if the improvements are in the right-of-way, each permittee shall procure a public improvement permit from the public works department on forms provided by the director of public works.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2026-30, passed June 22, 2026).
Full Breakdown
Aurora City Code § 138-368 makes it unlawful to construct, install, or place any storm drainage system extension or subsurface drainage structure within a public street, alley, or right-of-way, or to discharge into a public right-of-way or easement, without first obtaining a storm drainage system utility permit and stormwater quality discharge permit from Aurora Water. Separately, § 138-365 requires subdividers to dedicate a minimum 16-foot drainage easement (wider if a 100-year storm requires it) and to build minor drainage facilities at their own cost before final plat approval, all administered through Aurora Water's drainage master plan.
Violations & Fines
Constructing, installing, or discharging into city storm drainage infrastructure without both required Aurora Water permits is unlawful under § 138-368; noncompliant subdivisions can also be denied plat or replat approval under § 138-367.
Frequently Asked Questions
Do I need a permit to build or connect to a storm drain in Aurora?
Who administers Aurora's stormwater rules?
Sources & Official References
Other rules in Aurora
Compare Aurora to another location·View the Colorado environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Stormwater Management in Nearby Cities
How other cities in Arapahoe County handle stormwater management.