Bristol, PA Environmental Rules: Stormwater Management (2026)
Key Facts
- Ordinance
- Bristol Borough Stormwater Management Ordinance, Ord. No. 1358
- Approval needed
- Written drainage plan approval before building or occupancy permit
- Impervious exemption
- 1,200, 2,500 or 5,000 square feet by parcel size
- Earth disturbance exemption
- Under 5,000 square feet
- Maximum fine
- $1,000 per violation; each day separate
- Appeal deadline
- 30 days from the Borough's action
Summary
Chapter 26, Part 1 of the Bristol Borough Code, the Bristol Borough Stormwater Management Ordinance, regulates land development, subdivision, earth disturbance, new impervious surfaces and building additions, plus every discharge into the Borough's separate storm sewer system. Violations carry a fine of not more than $1,000 per violation.
1. All regulated activities and all activities that may affect stormwater runoff, including land development and earth disturbance activity, are subject to regulation by this Part. 2. All discharges entering into the municipality's separate storm sewer system are subject to regulation by this Part. 3. The following activities are defined as "regulated activities" and shall be regulated by this Part: A. Land development. B. Subdivision. C. Redevelopment. D. Earth disturbance activities. E. Construction of new or additional impervious or semi-pervious surfaces (roads, driveways, parking lots, patios, tennis courts, etc.). F. Construction of new buildings or additions to existing buildings. G. Diversion or piping of any natural or man-made stream channel. H. Installation of BMPs and/or stormwater management facilities or appurtenances thereto.
Full Breakdown
Part 1 of Chapter 26 is titled Delaware River South Watershed Stormwater Management and may be cited as the Bristol Borough Stormwater Management Ordinance. It was adopted as Ord. No. 1358 on 9/12/2022 and repealed the former Chapter 26 adopted by Ord. 1232 on 2/12/2007.
Section 26-104 sets the reach. All regulated activities and all activities that affect stormwater runoff are subject to the Part. Regulated activities are land development, subdivision, redevelopment, earth disturbance, construction of new or additional impervious or semi-pervious surfaces such as roads, driveways, parking lots, patios and tennis courts, new buildings or additions, diversion or piping of a stream channel, and installation of BMPs or stormwater facilities. The prohibitions on discharges apply to every discharge into the separate storm sewer system regardless of project type, impervious area or earth disturbance, for new and existing discharges alike.
Approval comes first. Under § 26-141, preliminary or final approval of subdivision and land development plans, any building or occupancy permit, and the start of any land disturbance cannot proceed until the applicant has written approval of a drainage plan from the Borough. Section 26-142 exempts small projects by parcel size: 1,200 square feet of impervious area for a parcel under 1/4 acre, 2,500 square feet from over 1/4 acre to 1 acre, and 5,000 square feet over 1 acre. Earth disturbance under 5,000 square feet is also exempt.
Day-to-day rules reach homeowners too. Section 26-181 bars discharges into the storm sewer system that are not composed entirely of stormwater, with listed exceptions such as firefighting flows, noncontaminated irrigation water and residential vehicle wash water where cleaning agents are not used. Section 26-182 says roof drains are not connected to streets, sanitary or storm sewers or roadside ditches, though the Borough can permit a connection case by case. Section 26-183 bars altering, filling or removing any existing BMP without the Borough's written approval.
Violations & Fines
Section 26-195 sets a fine of not more than $1,000 for each violation, recoverable with costs, with each day a separate offense and penalties cumulative. The Borough, through its solicitor, can also seek injunctions or mandamus. Section 26-194 declares any violation a public nuisance. Appeals go to the Borough's governing body or Zoning Hearing Board within 30 days (§ 26-196), then to the Bucks County Court of Common Pleas within 30 days.
Frequently Asked Questions
Does a new driveway or patio in Bristol Borough fall under the stormwater ordinance?
What size projects are exempt from the drainage plan requirement?
Can I connect my roof drain to the street or storm sewer?
What can legally go into the Borough storm sewer system?
What is the penalty and how do I appeal?
Sources & Official References
Other rules in Bristol
Compare Bristol to another location·View the Pennsylvania environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.