Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing chapter
Ch. 19, Stormwater Management Ordinance
Adopted
Ord. 2023-01, 4/19/2023
Applies to
New development, redevelopment, earth disturbance
Penalty
Up to $1,000 per violation per day
Enforcement
Municipal Engineer
Right-of-entry compliance window
24 hours (§ 19-902.3)
Appeal window
30 days to Board of Supervisors

Summary

Franklin Township's Stormwater Management Ordinance, Chapter 19 (Ord. 2023-01, 4/19/2023), regulates new development, redevelopment and earth-disturbance activities township-wide. Building and grading permits are conditioned on meeting the chapter's site-plan and BMP standards, enforced by the Municipal Engineer with a $1,000-per-day penalty.

§ 19-105. Applicability. ... 1. The following activities are regulated by this chapter: A. All regulated activities as defined in this chapter, including, but not limited to, new development, redevelopment, and earth disturbance activities that are located within the municipality shall be subject to regulation by this chapter. B. When a building and/or grading permit is required for any regulated activity on an existing parcel or approved lot created by a subdivision and/or improved as a land development project, issuance of the permit shall be conditioned upon adherence to the terms of this chapter.

Full Breakdown

), the Second Class Township Code, and the Pennsylvania Municipalities Planning Code. Section 19-105 makes the chapter applicable to all regulated activities, including new development, redevelopment and earth-disturbance activities located in the township, and conditions issuance of any building or grading permit on adherence to the chapter's terms. 1, measured from the chapter's adoption date or, where an earlier township ordinance already applied, from December 18, 2013. Roof drain, sump pump and foundation drain discharges are separately restricted from sanitary sewers under Part 8, and any tampering with an approved BMP or conveyance without written township approval violates § 19-805.

Enforcement sits with the Municipal Engineer or a designee under § 19-903, who can order corrective notices, suspend or revoke permits under § 19-904, and require monitoring, remediation or restoration. Section 19-901 declares any violation a public nuisance, with each day of continuing violation and each violated section treated separately. Section 19-902 gives township officers a right of entry to inspect stormwater controls, and failing to grant access within 24 hours of notice is itself a violation. Penalties under § 19-905 reach $1,000 per violation, prosecuted as a summary offense before a Magisterial District Judge, and the township may also pursue injunctive relief.

Aggrieved landowners can appeal an enforcement action to the Board of Supervisors within 30 days under § 19-906, and further appeal to the county court of common pleas within 30 days of that decision.

Violations & Fines

Any Chapter 19 violation is declared a public nuisance under § 19-901. Section 19-905 sets a fine of not more than $1,000 per violation, prosecuted as a summary offense before a Magisterial District Judge, with each day of a continuing violation treated as a separate offense. The township may also seek injunctive or mandamus relief through its Solicitor.

Frequently Asked Questions

What triggers Franklin Township's stormwater ordinance?
Section 19-105 covers any new development, redevelopment or earth-disturbance activity in the township; a building or grading permit is conditioned on meeting the chapter's stormwater management site-plan requirements.
Who enforces Franklin Township's stormwater rules?
The Municipal Engineer or a designated officer enforces Chapter 19 under § 19-903, with authority to suspend or revoke permits and order corrective work under § 19-904.
What's the fine for violating the stormwater ordinance?
Section 19-905 sets a fine of not more than $1,000 for each violation, prosecuted as a summary offense before a Magisterial District Judge, with each day of a continuing violation counted separately.
Can a landowner refuse a township stormwater inspection?
No. Section 19-902 lets township officers enter property to inspect stormwater controls, and failing to grant access within 24 hours of notice is itself a violation.

Sources & Official References

Other rules in Franklin Township

All Franklin Township rules

Compare Franklin Township to another location·View the Pennsylvania environmental rules overview

Get notified when Stormwater Management in Franklin Township, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.