Haverford, PA Environmental Rules: Stormwater Management (2026)
Key Facts
- Governing chapter
- Haverford Township Code Ch. 78, Art. II (Ord. No. 3000-2024)
- Plan required
- Approved SWM site plan before any regulated activity begins
- Plan validity
- Maximum five years from approval (§ 78-32)
- Access for inspection
- Owner must grant access within 24 hours of notification
- Penalty
- Misdemeanor, up to $1,000 per violation or 90 days, or both
- Appeal
- 30 days to the Board of Commissioners, then 30 days to Common Pleas
Summary
In Haverford Township, Delaware County, Pennsylvania, no regulated activity may begin until the township approves a stormwater management site plan. Chapter 78, Article II requires sites to minimize runoff and impervious surfaces, and a violation is a misdemeanor with a fine of up to $1,000 per violation.
A. Applicants proposing regulated activities in Haverford Township which do not fall under the exemption criteria shown in § 78-18 shall submit a stormwater management site plan consistent with this article and the applicable watershed stormwater management plan to Haverford Township for review. The stormwater management criteria of this article shall apply to the total proposed development even if development is to take place in stages. B. The applicant is required to design the site to minimize surface discharge of stormwater and the creation of impervious surfaces in order to maintain, as much as possible, the natural hydrologic regime. ... M. No regulated activity within the municipality shall commence until the municipality issues approval of a SWM plan, which demonstrates compliance with the requirements of this article.
Full Breakdown
Article II of Chapter 78 of the Haverford Township Code, adopted 11-12-2024 as Ord. No. 3000-2024, governs stormwater. Section 78-31 requires any applicant whose project is not exempt under § 78-18 to submit a stormwater management (SWM) site plan consistent with the applicable watershed plan. The criteria apply to the whole development even if it is built in stages. Applicants must design to minimize surface discharge and impervious surfaces, preserve natural flow conditions, and follow the sequencing in § 78-35. Techniques in Appendix E (Low-Impact Development) and green infrastructure are to be prioritized, and designers use the Pennsylvania Stormwater Best Management Practices Manual, with the most restrictive standard controlling in a conflict.
A new concentrated discharge onto or through neighboring land triggers a further requirement in § 78-31(V): a drainage easement or other legal agreement, and a conveyance designed to avoid erosion, flooding or other damage. Approval of an SWM site plan lasts a maximum of five years, and the township can set a shorter term (§ 78-32). Permanent BMPs carry operation and maintenance duties under §§ 78-48 through 78-55, and § 78-56 covers prohibited discharges and connections.
The township can enter property on presentation of credentials to inspect controls and BMPs, and an owner who does not grant access within 24 hours of notification commits a violation (§ 78-60). The Township Engineer handles inspections, and an occupancy permit is not issued without the certification of completion (§ 78-66). Anyone aggrieved by township action can appeal to the Board of Commissioners within 30 days, then to the County Court of Common Pleas within 30 days of the Board's decision (§ 78-67).
Violations & Fines
Section 78-64 makes any violation of Article II a misdemeanor, punishable on conviction by a fine of not more than $1,000 for each violation, recoverable with costs, or imprisonment of not more than 90 days, or both. Each day is a separate offense. Violations are also a public nuisance (§ 78-61), permits can be suspended or revoked (§ 78-63), and the township can seek injunctions through its solicitor.
Frequently Asked Questions
When do I need a stormwater management plan in Haverford Township?
What rules apply when runoff will cross my neighbor's land?
How long does an approved stormwater plan last?
How do I appeal a stormwater decision in Haverford Township?
Sources & Official References
Other rules in Haverford
Compare Haverford to another location·View the Pennsylvania environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.