Ada County, ID Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Drainage study/plan
prepared by Idaho-licensed engineer
Must document
irrigation ditches and laterals on site
Re-routing irrigation facilities
requires all affected owners' consent
Rainwater harvesting trigger
commercial/industrial over 10,000 sq ft
Residential rainwater harvesting trigger
homes over 25,000 sq ft
Cistern/rain barrel minimum
40 gallons storage

Summary

New development in unincorporated Ada County must submit an engineer-prepared drainage study and drainage plan under Section 8-3-5(B) before the county issues a zoning certificate, showing where stormwater is routed, sized to the upstream drainage basin, and coordinated with any irrigation ditches or laterals crossing the site.

City-specific rules exist: Boise has its own stormwater management rules that differ from Ada County's county-level regulations. If you live in Boise, check the city-specific page instead.

All required drainage studies and drainage plans shall be based upon peak and total discharge estimates and shall be submitted by a professional engineer licensed in the state of Idaho... When drainage courses and irrigation facilities exist on site, documentary evidence of consent to re-routings by all interested landowners and drainage and irrigation entities affected and having rights to, and in, those facilities shall be provided.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-15: Code current through: Ord. 1018, passed 3-24-2026).

Full Breakdown

Section 8-3-5(B), Infrastructure: Drainage, requires that "all required drainage studies and drainage plans shall be based upon peak and total discharge estimates" and be prepared and submitted by a professional engineer licensed in Idaho. The drainage study itself must map the site's existing drainage and irrigation features, including ditches, watercourses and drainage structures; document soil permeability and geologic materials; size the upstream drainage basin; note site topography and slope; flag any surface water or potable water supply well within 100 feet; and describe the proposed use's potential contaminants along with any past soil or groundwater contamination.

Once the County Engineer requires a formal drainage plan as a condition of approval, that plan must be drawn to scale showing all proposed grading, the essential elements of the drainage system such as storm drains, catch basins, pumps and seepage beds, and flow arrows or contours showing exactly where stormwater will be routed on and off the property, including flows entering from adjoining land. Where drainage courses or irrigation facilities already exist on site, most notably the irrigation-district laterals and ditches running through many suburban Ada County subdivisions, the applicant must produce documentary evidence that every affected landowner and irrigation or drainage entity has consented to any re-routing before the County Engineer will approve the plan.

The same infrastructure chapter lets the County Engineer credit green stormwater infrastructure, rainwater harvesting or pervious pavement toward reducing required drainage improvements, but only if the applicant documents the reduction with accepted engineering methods and commits to a maintenance plan. Commercial or industrial buildings over 10,000 square feet, and single-family homes over 25,000 square feet, must also include working rainwater harvesting such as cisterns or rain barrels storing at least 40 gallons.

Violations & Fines

Development Services will not issue a zoning certificate without an approved drainage plan when the County Engineer has required one, and re-routing an existing irrigation ditch or lateral without documented consent from every affected landowner and irrigation entity blocks plan approval outright. Agricultural structures are the only use exempted from the underground-utility and drainage requirements of this section.

Frequently Asked Questions

Do I need an engineer for a drainage plan in unincorporated Ada County?
Yes. Section 8-3-5(B) requires all required drainage studies and drainage plans to be based on peak and total discharge estimates and submitted by a professional engineer licensed in the state of Idaho.
What happens to the irrigation ditch running through my subdivision lot?
If you want to re-route an existing irrigation or drainage facility, you must provide documentary evidence that every interested landowner and irrigation or drainage entity with rights in it has consented before the County Engineer will approve the plan.
Is pervious pavement allowed instead of a full drainage plan?
Pervious pavement, rainwater harvesting and other green stormwater infrastructure can reduce required drainage improvements, but only if the County Engineer finds the reduction is backed by accepted engineering methods and an ongoing maintenance plan.
Does every new house need rainwater harvesting?
No, only single-family residences larger than 25,000 square feet and commercial or industrial structures larger than 10,000 square feet must include rainwater harvesting such as cisterns or rain barrels storing at least 40 gallons.

Sources & Official References

Other rules in Ada County

All Ada County rules

Compare Ada County to another location·View the Idaho environmental rules overview

Get notified when Stormwater Management in Ada County, ID changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Cities Across Ada County