Key Facts

Min. entrance pipe
15 inches diameter (§ 95.11(B)(2))
Min. pipe length
20 feet
Catch basin spacing
~50 feet on 15-inch pipe
Major changes require
25-yr and 100-yr storm study
Fill slope required
6:1 to ditch flow line
Max fine
$500, misdemeanor (§ 95.99)

Summary

Any driveway or entrance connecting to a Kenton County road must meet the drainage standards in Code § 95.11: an entrance pipe no smaller than 15 inches in diameter and 20 feet long, catch basins roughly every 50 feet, and a licensed engineer's 25-year and 100-year storm analysis for any major drainage change.

These county ordinances apply to unincorporated areas of Kenton County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Any entrance whether in a rural or urban area, shall not obstruct or restrict the normal water drainage along or across the county road, unless suitable provisions are made therefor. The Public Works Superintendent shall be satisfied that the type, size, and installation of the drainage features proposed in the application are adequate for present and foreseeable future requirements and have a reasonable life span. ... The size, length and type of the entrance pipe shall be as required by the Public Works Superintendent, but in no case shall be less than 15 inches in diameter and not less than 20 feet in length. ... Any proposal to alter or significantly increase a drainage area, run-off factors or change in any way a drainage structure must be accompanied by a complete drainage survey (upstream and downstream) based on a 25-year and 100-year storm with hydraulic analysis of all affected drainage structures in the area and prepared by a registered, licensed engineer.

Full Breakdown

11(A) sets the baseline rule for every entrance built along a Kenton County road: it "shall not obstruct or restrict the normal water drainage along or across the county road, unless suitable provisions are made therefor," and the Public Works Superintendent must be satisfied the proposed drainage features are adequate for present and future needs and have a reasonable life span, including approval of the pipe material itself. Subsection (B) then itemizes ten specific requirements. Entrance pipe cannot tie into existing roadway drainage structures unless junction boxes, manholes and catch basins are installed to county specifications, and the pipe itself must be "not less than 15 inches in diameter and not less than 20 feet in length," per Public Works standards and standard drawings RDB 110-01 or 111-02.

Where long pipe runs are used, catch basins or clean-out boxes go in at roughly 50-foot intervals for 15-inch pipe, and gratings must keep driveway water from flowing over sidewalks or the roadway. Fill placed against an existing road must slope 6:1 down to the ditch or a three-foot depth, with french or toe drains as needed. Any proposal that significantly alters a drainage area requires "a complete drainage survey (upstream and downstream) based on a 25-year and 100-year storm with hydraulic analysis," prepared by a registered, licensed engineer.

12 goes further, making a permittee whose development overloads downstream county drainage facilities responsible for either fixing those facilities or building an on-site retention basin, at the permittee's own risk for resulting damage claims.

Violations & Fines

Building or altering a driveway or entrance that fails the § 95.11 drainage standards, or that overloads downstream drainage facilities without the fix or retention basin § 95.12 requires, is a misdemeanor under § 95.99, punishable by a fine of not more than $500 and enforced by the Public Works Superintendent under § 95.14.

Frequently Asked Questions

What are Kenton County's driveway drainage pipe requirements?
Code § 95.11(B)(2) sets a floor: entrance pipe must be "not less than 15 inches in diameter and not less than 20 feet in length," as required by the Public Works Superintendent, with pipe specifications and headwalls meeting county standard drawings RDB 110-01 or 111-02.
Who reviews driveway drainage plans in Kenton County?
The Public Works Superintendent reviews and approves entrance drainage under § 95.11(A), who must be satisfied that the type, size and installation of proposed drainage features are adequate for present and future needs, and the whole policy is administered under § 95.14.
What if my development overloads downstream county drainage?
Section 95.12 makes the permittee responsible for either modifying or replacing the inadequate downstream drainage facility, or building an on-site retention basin, to the Public Works Department's satisfaction, and the permittee bears any resulting lawsuits or damage claims.

Sources & Official References

Other rules in Kenton County

All Kenton County rules

Compare Kenton County to another location·View the Kentucky environmental rules overview

Get notified when Stormwater Management in Kenton County, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.