Key Facts

Exempt disturbance threshold
5,000 sq ft or less
Redevelopment impervious cut
At least 50% reduction
Permit validity
2 years, 1-year extension
Criminal fine
Up to $1,000 per violation
Civil penalty option
Up to $5,000 plus injunction
Enforcing agency
Dept. of Environmental Protection and Sustainability
Governing law
County Code § 33-4-102, § 33-4-104

Summary

Baltimore County bars developing or redeveloping any site without stormwater management measures that control runoff, using environmental site design to the maximum extent practicable before any structural pond or filter is built. The Department of Environmental Protection and Sustainability enforces the requirement under County Code Article 33, Title 4, with the Department of Public Works and Transportation assisting.

These county ordinances apply to unincorporated areas of Baltimore County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Except as provided in this title, a person may not develop or redevelop any site without providing for appropriate stormwater management measures that control or manage stormwater runoff from the site. The stormwater management measures shall be:(i)Consistent with the Design Manual; and(ii)Constructed in accordance with a plan approved by the Department. ... Criminal. A person who violates any provision of this title is guilty of a misdemeanor and on conviction is subject to a fine not exceeding $1,000 for each violation. ... Civil.(1)As an alternative to a criminal action, the county may bring a civil action against any person for any violation of this title.(2)The action may seek the imposition of a civil penalty of not more than $5,000 against the person, an injunction to prohibit the person from continuing the violation, or both.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 29 | Zoning Regulations: Supplement 10).

Full Breakdown

Section 33-4-102 sets the purpose of Article 33, Title 4: managing stormwater through environmental site design (ESD) "to the maximum extent practicable," using structural best management practices only when ESD cannot do the job, in order to reduce local flooding, stream channel erosion, and property damage. Section 33-4-104(a) makes the rule concrete: a person may not develop or redevelop a site without stormwater management measures that are consistent with the county's Design Manual and built under a plan the Department of Environmental Protection and Sustainability has approved.

Small projects get relief: developments that disturb 5,000 square feet or less of land, agricultural land management, and minor additions to existing single-family homes are exempt under Section 33-4-104(b), but the Director must certify any claimed exemption in writing. Everything else goes through three plan stages under Section 33-4-107, concept, development, and final, each adding detail on drainage areas, impervious area, and required storage volumes for recharge, water quality, channel protection, and overbank flood control. A stormwater management permit under Section 33-4-108 cannot issue until security is posted, an environmental agreement is executed, and the Soil Conservation District has approved the erosion and sediment control plan; permits expire two years after issuance, with one-year extensions available on written request.

Redevelopment sites carry their own math: Section 33-4-105 requires cutting existing impervious area within the limit of disturbance by at least 50%, or treating an equivalent share with ESD, unless the applicant pays into the county's Stormwater Management Fund.

Violations & Fines

Section 33-4-115 makes any violation of the stormwater title a misdemeanor carrying a fine of up to $1,000 per violation, with each day of continued noncompliance charged as a separate offense. The county can instead bring a civil action seeking a penalty of up to $5,000 plus an injunction ordering the violation stopped. The Department of Environmental Protection and Sustainability enforces through Article 3, Title 6 code enforcement procedures, including correction notices and stop-work orders.

Frequently Asked Questions

Does every construction project in Baltimore County need a stormwater permit?
Most do. Section 33-4-104(a) prohibits developing or redeveloping a site without approved stormwater management measures. Small projects are exempt if they disturb 5,000 square feet or less of land, involve agricultural land management, or are minor additions to an existing single-family home, but the Department of Environmental Protection and Sustainability must certify the exemption in writing.
How long does a Baltimore County stormwater permit last?
Two years from the issue date under Section 33-4-108(e). If the permittee cannot finish within that window, the Department of Permits, Approvals and Inspections may grant a one-year extension on written request. Any additional work beyond what the approved plans cover requires amending the permit and paying an added fee first.
What is the penalty for skipping stormwater management approval?
Section 33-4-115 makes it a misdemeanor punishable by a fine up to $1,000 for each violation, with every day the violation continues counted separately. The county can instead sue civilly for up to $5,000 and an injunction stopping the work, and the Director of Environmental Protection and Sustainability enforces both routes under Article 3, Title 6 of the Code.

Sources & Official References

Other rules in Baltimore County

All Baltimore County rules

Compare Baltimore County to another location·View the Maryland environmental rules overview

Get notified when Stormwater Management in Baltimore County, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.