Piscataway, NJ Environmental Rules: Stormwater Management (2026)
Key Facts
- Governing chapter
- Piscataway Township Code Chapter 32, Article II
- Applies to
- Major development: 1+ acre disturbed or 1/4 acre impervious
- Maintenance plan
- Required for stormwater measures under § 32-13
- Stormwater utility fee
- $77 per equivalent residential unit annually
- Max penalty
- 60 days jail or $1,000 fine, § 32-14
- Last amended
- September 9, 2025 by Ordinance No. 2025-19
- Illicit connection fine
- $450 fine under § 32-3.5
Summary
Piscataway Township Code Chapter 32, Article II requires "major development," projects disturbing one acre of land or creating a quarter acre of new impervious or motor vehicle surface, to install green infrastructure best management practices for groundwater recharge, water quality and runoff-quantity control. The Township Council overhauled the article by Ordinance No. 2020-35 and most recently amended it September 9, 2025 by Ordinance No. 2025-19.
§ 32-4. SCOPE AND PURPOSE. ... Policy Statement. Flood control, groundwater recharge, and pollutant reduction shall be achieved through the use of stormwater management measures, including green infrastructure Best Management Practices (GI BMPs) and nonstructural stormwater management strategies. ... Purpose. ... The purpose of this article is to establish minimum stormwater management requirements and controls for "major development," as defined below in Section II. ... ... § 32-14. PENALTIES. ... Any person(s) who erects, constructs, alters, repairs, converts, maintains, or uses any building, structure or land in violation of this ordinance shall be subject to the following penalties: ... Maximum Penalty. For violation of any provision of this article, the maximum penalty upon conviction of the violation shall be by one or more of the following: 1. Imprisonment in the County Jail or in any place provided by the Township for detention of prisoners for a term not exceeding 60 days; or 2. A fine not exceeding $1,000.
Full Breakdown
Under § 32-4, the Township's stormwater management standards apply to non-residential major development, to the non-preempted aspects of residential major development, and to any major development the Township itself undertakes. "Major development" under § 32-5 means a project disturbing one acre or more of land since February 2, 2004, creating a quarter acre or more of regulated impervious surface since that date, creating a quarter acre or more of regulated motor vehicle surface since March 2, 2021, or a combination reaching a quarter acre. Applications submitted between March 2, 2021 and August 12, 2025 stay under the standards in effect on August 11, 2025.
Section 32-7 requires green infrastructure BMPs drawn from the tables keyed to the New Jersey Stormwater BMP Manual, with contributory drainage-area limits, and lets a waiver from strict compliance issue only where the applicant proves no other means exist and files an alternatives analysis. Underground and aboveground utility-line work and pedestrian trails up to 14 feet wide made of permeable material are exempt from the recharge, quality and quantity requirements. Every approved project must carry a maintenance plan for its stormwater measures under § 32-13, and the Township funds inspection and administration through a Stormwater Utility (§ 32-15) that bills a $77 per equivalent residential unit annual user fee (§ 32-16) on every developed property except those the Clean Stormwater and Flood Reduction Act exempts.
Illicit connections to the municipal storm sewer system are separately banned under § 32-3.3, enforced by the Police Department, carrying a $450 fine under § 32-3.5.
Violations & Fines
Piscataway Township Code § 32-14 makes it a violation to erect, construct, alter, repair, convert, maintain or use any building, structure or land contrary to the stormwater management article. The maximum penalty is imprisonment in the county jail for up to 60 days, a fine of up to $1,000, or both. Every distinct regulated activity performed in violation counts as a separate offense, and each day the violation continues is its own separate violation. The Township may also bring a civil action for injunctive relief in addition to any criminal penalty.
Frequently Asked Questions
Does my construction project need to meet Piscataway's stormwater rules?
What is the penalty for violating Piscataway's stormwater ordinance?
Does Piscataway charge a stormwater utility fee?
Sources & Official References
Other rules in Piscataway
Compare Piscataway to another location·View the New Jersey environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.