Ridgewood, NJ Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
§ 190-83, last amended 12/11/2024
Major development trigger
1/2 acre disturbed or 5,000 sq ft impervious surface
Required approach
Green infrastructure BMPs and low-impact development
Protected habitat check
Swamp pink and bog turtle habitat impacts avoided
Enforcing officials
Village Engineer and Public Works Director (§190-134)

Summary

The Village of Ridgewood regulates stormwater under § 190-83, requiring green infrastructure and nonstructural measures for flood control, groundwater recharge and pollutant reduction on every "major development" and "minor development." A major development is triggered by disturbing half an acre of land or creating 5,000 square feet of new impervious or motor vehicle surface since 2004.

Policy statement. Flood control, groundwater recharge, and pollutant reduction shall be achieved through the use of stormwater management measures, including green infrastructure best management practices (GI BMPs) and nonstructural stormwater management strategies. ... Purpose. The purpose of this section is to establish minimum stormwater management requirements and controls for "major development" and "minor development" as defined below in Subsection B. ... An individual development, as well as multiple developments that individually or collectively result in: (a) The disturbance of 1/2 acre (21,780 square feet) of land since February 2, 2004; (b) The creation of 5,000 square feet or more of "regulated impervious surface" since February 2, 2004;

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4854397; v35 updated 2026-04-22; through 04-22-2026).

Full Breakdown

Section 190-83, Stormwater management and flood protection, is Ridgewood's controlling stormwater ordinance, last amended December 11, 2024 by Ordinance No. 4025. Its policy statement commits the Village to flood control, groundwater recharge and pollutant reduction through green infrastructure best management practices (GI BMPs) and low-impact development, developed based upon each site's physical conditions and the anticipated quantity of potential pollutants. The section applies to non-residential major developments, the non-preempted parts of residential major developments, any major development the Village itself undertakes, and to minor developments as defined in Subsection B.

"Major development" is defined by numeric thresholds: disturbing one-half acre (21,780 square feet) of land, creating 5,000 square feet or more of regulated impervious surface, or 5,000 square feet or more of regulated motor vehicle surface, each measured since a 2004 or 2021 baseline date, or any combination of the two surface categories totaling 5,000 square feet. Every major development must incorporate a maintenance plan for its stormwater measures, and must avoid concentrating flow in a way that harms threatened or endangered species habitat identified in the state's Landscape Project or Natural Heritage Database, including the swamp pink and bog turtle. C. 2(f) control.

Violations & Fines

Enforcement of § 190-83 falls to the Village Engineer and Public Works Director under § 190-134C, who may investigate complaints, inspect sites and issue a summons to Municipal Court. Building, altering or maintaining a structure, or using land, in violation of Article IX is a misdemeanor under § 190-136, punishable under the penalty schedule in Chapter 1, General Provisions, Article I, with each day the violation continues treated as a separate offense.

Frequently Asked Questions

What counts as a "major development" under Ridgewood's stormwater rule?
Section 190-83B defines it as any project, alone or combined with related phases, that disturbs one-half acre (21,780 square feet) of land or creates 5,000 square feet or more of new impervious or motor vehicle surface since the applicable 2004 or 2021 baseline date.
Does Ridgewood require green infrastructure for stormwater control?
Yes. Section 190-83A's policy statement directs that flood control, groundwater recharge and pollutant reduction be achieved through green infrastructure best management practices and nonstructural strategies, developed based on each site's physical conditions and expected pollutant load.
Who enforces Ridgewood's stormwater ordinance?
The Village Engineer and Public Works Director enforce Article IX, which includes § 190-83, under § 190-134C. They can investigate violations, inspect properties with a warrant if needed, and issue a Municipal Court summons for noncompliance.
Do small home projects in Ridgewood have to follow the stormwater ordinance?
Yes. Section 190-83 also applies to "minor development," and § 190-67N separately requires a stormwater management application for any addition, pool or improvement adding at least 200 square feet of impervious surface, even where the major-development thresholds are not met.

Sources & Official References

Other rules in Ridgewood

All Ridgewood rules

Compare Ridgewood to another location·View the New Jersey environmental rules overview

Get notified when Stormwater Management in Ridgewood, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.