Key Facts

Permit required for
Retaining walls built in the street right-of-way
Permit fee
$40.00 per permit
Curb clearance rule
4 feet minimum when no sidewalk exists
Issuing authority
Public works director
First offense
Civil infraction under RMC § 10.02.050(E)
Repeat offense
Misdemeanor on 3rd violation, RMC § 1.30.010

Summary

In the City of Richland, Washington, anyone building a retaining wall inside a street right-of-way must get a permit from the public works director before work starts, under Richland Municipal Code § 12.12.010. The permit fee is $40.00. The director must refuse the permit if the fronting street isn't fully improved, the wall would create a traffic sight hazard, or, where there's no sidewalk yet, the wall would sit closer than four feet to the curb.

§ 12.12.010. Permit required. ... It is unlawful for any person, firm or corporation to construct a retaining wall in any street right-of-way in the city without first having obtained from the public works director a permit for the construction of a retaining wall. The fee for each permit shall be $40.00. ... ... C. When the street in front of the property to be served by the proposed retaining wall is improved but there is no sidewalk abutting said property, no permit shall be issued for a retaining wall closer than four feet to the curb. ... ... § 12.12.060. Violations – Penalties. Any person who has violated any provision of this chapter shall have committed a civil infraction subject to a civil penalty as set forth in RMC § 10.02.050(E). Provided, if the same violator has been found to have committed an infraction violation for the same or similar conduct two separate times, with the violations occurring at the same location and involving the same or similar sections of the Richland Municipal Code or other similar codes, the third or subsequent violation shall constitute a misdemeanor, punishable as provided in RMC § 1.30.010 for criminal offenses.

Full Breakdown

Richland Municipal Code § 12.12.010 makes it unlawful to construct a retaining wall in any city street right-of-way without a permit from the public works director, and the fee for each permit is $40.00. This chapter governs walls built in the right-of-way itself, not general residential landscaping walls set entirely on private property. Under § 12.12.020, the application must go on city forms and show the wall's type and location, the start and completion dates, and an undertaking to hold the city harmless from liability tied to the wall's construction, maintenance, or failure.

Section 12.12.030 lists three mandatory refusal grounds: the fronting street isn't yet fully improved (unless the director finds the wall won't interfere with a future street improvement); the wall would create a traffic hazard by obstructing visibility; or, where the street is improved but no sidewalk fronts the property, the wall would sit closer than four feet from the curb. Under § 12.12.040, the city can require the property owner to remove a right-of-way retaining wall at any time it's needed to improve the street or reach a public utility system; if the owner doesn't act within 30 days of notice, the city may remove it and bill the owner.

Per § 12.12.050, the city owes no reimbursement for loss or damage from that removal. Development Services and the public works director administer these permits, and enforcement runs alongside the city's broader right-of-way rules under Chapter 12.08 for any work that also disturbs city infrastructure.

Violations & Fines

Building or maintaining a right-of-way retaining wall without the required § 12.12.010 permit, or violating any provision of Chapter 12.12, is a civil infraction carrying a civil penalty under RMC § 10.02.050(E). If the same violator repeats the same or a similar violation at the same location two separate times, the third or later violation becomes a misdemeanor, punishable under RMC § 1.30.010 for criminal offenses rather than as a civil infraction.

Frequently Asked Questions

Do I need a permit for a retaining wall entirely on my own property in Richland?
Richland Municipal Code § 12.12.010 only requires this permit for a retaining wall built in a city street right-of-way. A wall the owner keeps fully on private property, away from the right-of-way, doesn't trigger this particular permit, though other city building and zoning requirements can still apply to it separately.
How much does a Richland retaining wall permit cost?
The fee for each retaining wall permit is $40.00, payable when the owner applies to the public works director under § 12.12.010. The application under § 12.12.020 must show the wall's type, location, and construction schedule, plus an agreement to hold the city harmless for any liability tied to the wall.
Can Richland make me remove my retaining wall later?
Yes. Under § 12.12.040, the city can require the property owner to remove a right-of-way retaining wall whenever removal is needed to improve the street or access a public utility system. If the owner doesn't remove it within 30 days of notice, the city can remove it and bill the owner for the cost.

Sources & Official References

Other rules in Richland

All Richland rules

Compare Richland to another location·View the Washington fence regulations overview

Get notified when Retaining Walls in Richland, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Retaining Walls in Nearby Cities

How other cities in Benton County handle retaining walls.

Kennewick, WA
Some Restrictions