Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Exemption threshold
4 feet unsupported excavation height
Condition for exemption
Wall has a valid building permit
Over 4 feet
Full grading permit required
Engineered grading trigger
Wall supports other engineering works
Unpermitted grading
Declared a public nuisance
Investigation fee
Equal to the permit fee owed

Summary

Spokane Valley exempts retaining wall excavation from a grading permit only when the wall itself is authorized by a valid building permit and the unsupported excavated height stays at four feet or less. Anything taller triggers full grading permit review under SVMC § 24.50.020(C).

An excavation below finished grade for basements and footings of a building, retaining wall, or other structure authorized by a valid building permit; provided excavation having an unsupported height greater than four feet after the completion of such structure shall not be exempt. Use of, placement, and fill made with any material from any such excavation shall be subject to the requirements of Chapter 24.50 SVMC and shall not be exempt except as otherwise provided herein;

Full Breakdown

50 SVMC regulates land disturbing activities separately from the building permit for the wall itself. 50's requirements even when the cut itself is exempt. 030(A)(13), which requires an engineered grading permit for 'grading to support other engineering works such as, but not limited to, tanks, towers, machinery, retaining walls, and paving,' so a taller or load-bearing wall can trigger the engineered track even beyond the four-foot excavation threshold. 010(I).

Violations & Fines

Section 24.50.010(J) declares that 'unless exempt, any land disturbing activity performed without a permit or in violation of any applicable code or permit condition shall be considered hazardous and a public nuisance, subject to all enforcement actions and penalties as found in SVMC Title 17,' plus an investigation fee equal to the permit fee that would have applied. The city's general penalty at § 1.10.010 also applies: a misdemeanor with fines up to $1,000 and 90 days in jail, or a civil infraction of at least $250, with each day a separate offense under § 1.10.020.

Frequently Asked Questions

Do I need a permit to build a retaining wall in Spokane Valley?
The wall itself needs a building permit. Its excavation is separately exempt from a grading permit under § 24.50.020(C) only if the unsupported cut is four feet or less; taller unsupported excavation is never exempt and needs its own grading permit.
What happens if my retaining wall excavation is deeper than 4 feet?
It loses the § 24.50.020(C) exemption entirely and needs a grading permit, and a wall built to support other engineering works can also require the engineered grading track described at § 24.50.030(A)(13).
What if I grade for a retaining wall without a permit?
Section 24.50.010(J) declares unpermitted land disturbing activity a public nuisance subject to Title 17 enforcement, plus an investigation fee equal to the permit fee that would have applied, on top of the city's general misdemeanor and civil infraction penalties.

Sources & Official References

Other rules in Spokane Valley

All Spokane Valley rules

Compare Spokane Valley to another location·View the Washington fence regulations overview

Get notified when Retaining Walls in Spokane Valley, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.