Corpus Christi, TX Filming & Production: Street Closures (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing provision
Sec. 36-86(c)
Traffic plan review fee
$100.00
Plan must be prepared by
Texas-licensed professional engineer
Right-of-way charge
Sec. 53-195 occupancy charges apply
Added staffing costs due
Within 7 days of notice (Sec. 36-86(b))

Summary

A Corpus Christi filming permit that needs a street closure or traffic control requires TMUTCD-compliant traffic control plans from a Texas-licensed professional engineer, a $100 plan review fee, and payment of the Sec. 53-195 right-of-way occupancy charges, all under Sec. 36-86(c). The applicant bears full responsibility for pedestrian and vehicle safety.

(c)Traffic engineering. It shall be the duty of each applicant to make provisions for the safe crossing of pedestrians and the orderly movement of vehicular traffic in accordance with the Texas Manual on Uniform Traffic Control Devices (TMUTCD). If a street closure or traffic control is required, the applicant shall be responsible for paying occupancy charges required by section 53-195. Traffic control plans must be obtained from a professional engineer licensed in the State of Texas and submitted to the city for approval. A review fee of one hundred dollars ($100.00) will be charged for the required review of traffic control plans submitted by an applicant's consultant professional engineer. The applicant is responsible for obtaining services for traffic control devices.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 44).

Full Breakdown

Sec. 36-86(c) makes it the applicant's duty to provide for the safe crossing of pedestrians and the orderly movement of vehicular traffic in accordance with the Texas Manual on Uniform Traffic Control Devices. Where a street closure or other traffic control is required for the shoot, the applicant must pay the occupancy charges set by Sec. 53-195 for use of the public right-of-way, on top of the filming permit itself. The traffic control plans supporting that closure must come from a professional engineer licensed in Texas and be submitted to the city for approval, and the city charges a $100 review fee for that plan review.

The applicant is also responsible for obtaining the services needed to actually place the traffic control devices in the field, not just the paper plan. Sec. 36-86(a) and (b) layer on top of the traffic-control duty: the applicant must pay for any police, fire, or other city personnel assigned to the production, whether specifically requested or not, and the chief of police or fire chief can add staffing requirements at any time if needed for public safety, with those added costs due within seven days of notice.

Violations & Fines

Closing a Corpus Christi street for filming without the required TMUTCD-compliant traffic control plan, the professional engineer's approval, or payment of the Sec. 53-195 occupancy charges violates the material terms of the filming permit, which under Sec. 36-84(g) subjects the applicant to the Code's general penalty in Sec. 1-6, up to a $500 fine, and the city can also bill the applicant directly for any additional police or fire staffing costs incurred.

Frequently Asked Questions

What does Corpus Christi require to close a street for filming?
Sec. 36-86(c) requires traffic control plans that comply with the Texas Manual on Uniform Traffic Control Devices, prepared by a professional engineer licensed in Texas, submitted for city approval with a $100 review fee, plus payment of the right-of-way occupancy charges set by Sec. 53-195.
Who pays for police officers assigned to a Corpus Christi film shoot?
The applicant does. Sec. 36-86(a) makes the production responsible for the cost of any police, fire, traffic engineering, or other city personnel assigned to the project, whether the applicant specifically requested them or not.
Can Corpus Christi require extra police staffing mid-production?
Yes. Sec. 36-86(b) lets the chief of police or fire chief add staffing requirements at any point during the project if needed for public safety, and the applicant must pay the added cost within seven days of being notified.

Sources & Official References

Other rules in Corpus Christi

All Corpus Christi rules

Texas rules heatmap·Compare Corpus Christi to another location·View the Texas filming & production overview

Get notified when Street Closures in Corpus Christi, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.