Denton, TX Filming & Production: Street Closures (2026)
Key Facts
- Advance filing
- 14 working days before closing
- Petition deadline
- 5 days before closing
- Required document
- Professional barricade plan
- Traffic control
- Coordinated with Denton Police
- Enforcing office
- City manager's office
Summary
Filming that blocks a public right-of-way in Denton requires a separate street closing permit filed at least 14 working days ahead, with a barricade plan and a signed neighbor petition.
An applicant for a film permit must apply for a street closing permit as provided herein if, during any portion of the filming, access to public rights-of-way are to be obstructed or denied. Any permit issued under this section may be incorporated into a film permit issued under section 16-181 of this Code.
(a)Application. An applicant must submit a request for a street closing permit at least fourteen (14) working days prior to the requested closing. The fourteen-day requirement may be waived at the discretion of the city manager.(b)Barricade plan. Upon application, the applicant must simultaneously submit a sketch indicating the area to be closed and the location of all properties adjacent to the area being closed. A traffic control plan must be submitted to the city for review and approval. The barricade plan, provided by a professional barricade company, must indicate placement of barricades, types of barricades, warning and detour signs, and shall conform with the requirements of the Barricade Manual adopted by section 25-92 of this Code, all applicable laws, regulations, and city policies, and must be consistent with good engineering practice.(c)Street closing petition. The applicant must circulate a petition and obtain signatures, names and addresses from all abutting property owners, tenants, and merchants potentially affected by the street closing.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 37 Update 1 | Development Code: Supplement 27).
Full Breakdown
Under Sec. 16-182 of the Denton Code of Ordinances, a film permit alone does not authorize blocking a street. If any portion of filming will obstruct or deny access to a public right-of-way, the applicant must also apply for a street closing permit, submitted at least 14 working days before the requested closing (waivable at the city manager's discretion). The application must include a barricade plan from a professional barricade company conforming to the city's Barricade Manual, plus a traffic control plan reviewed by the City of Denton Police Department, who may require paid off-duty officers to direct traffic. The applicant must also circulate a petition to abutting property owners, tenants, and merchants documenting their consent or opposition, filed with the city manager five days before closing.
Violations & Fines
The underlying film permit is issued under Sec. 16-181; violating any provision of the film-permit article, including closing a street without the required permit, is a misdemeanor under Sec. 1-12, with each day a separate offense, and can cost the production its filming privileges in the city.
Frequently Asked Questions
Do I need this if I already have a film permit?
Can neighbors block my street closure?
Sources & Official References
Other rules in Denton
Texas rules heatmap·Compare Denton to another location·View the Texas filming & production overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.