Boston, MA Historic Preservation: Historic-Cultural Monuments (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

District created
Ord. 1983 c. 18
Commission size
5 members, 3 alternates
Hearing notice period
8 business days to notice
Decision deadline
30 business days from filing
Appeal deadline
20 days to Superior Court
Fine range
$50-$500 per day

Summary

Boston's Bay Village Historic District, created by ordinance under M.G.L. Chapter 40C, requires a Certificate of Appropriateness, Hardship, or Non-Applicability from a dedicated Historic District Commission before any exterior alteration, demolition, or new construction inside the district. The Building Commissioner cannot issue a permit until that certificate exists.

No building, or property, or structure within the Historic District shall be constructed, demolished, moved or altered in any way that affects exterior architectural features, and no building shall be moved into the Historic District unless the Commission shall first have issued a certificate of appropriateness, a certificate of hardship or a certificate of non-applicability with respect to such construction, demolition, alteration or movement. The Building Commissioner shall not issue a permit within an Historic District unless one of the certificates noted above has first been issued by the Commission or the proposed improvement is exempted from these provisions by Subsection 7-3.5.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-2: Current through Ordinance 2025 C. 14, passed 11-5-2025).

Full Breakdown

L. Chapter 40C) and Chapter 772 of the Acts of 1975. 3 creates a five-member Historic District Commission, plus three alternates, appointed by the Mayor and confirmed by the City Council, drawing nominees from the Society for the Preservation of New England Antiquities, the Boston Society of Architects, the Boston Landmarks Commission, the Greater Boston Real Estate Board, and district residents. 4 bars construction, demolition, moving, or exterior alteration of any building, property, or structure in the district, and bars the Building Commissioner from issuing a permit, unless the Commission first issues a certificate.

6 sets the process: within eight business days of filing, the Commission identifies materially affected properties and, absent a written waiver, holds a public hearing on notice by mail; it must decide within 30 business days of filing (or a longer period the applicant allows in writing), weighing historical and architectural value, style, and compatibility with neighboring structures. 5 exempts temporary structures/signs, ordinary maintenance that changes nothing structurally, work the Building Commissioner certifies is required for public safety, and a specific Urban Renewal Parcel (R-7) under a 1980 developer's kit. 7 allows an aggrieved applicant to appeal a Commission determination to Suffolk Superior Court within 20 days of the City Clerk's notice filing.

Violations & Fines

Unauthorized exterior work, or continuing a violation after a Commissioner's notice to desist, is punishable by a fine of $50 to $500 per day under Section 7-3.8, with each day of continuing violation a separate offense. The Commission may also petition Suffolk Superior Court to restrain the work and order removal or restoration of the unauthorized exterior feature.

Frequently Asked Questions

Do I need approval to repaint or repair my Bay Village home?
Ordinary maintenance or repair that involves no change in design, material, or outward appearance is exempt from Commission review under Section 7-3.5(B). Anything that changes the exterior architectural feature, such as new siding or window replacement, needs a certificate first.
What is a Certificate of Hardship?
If the Commission fails to rule within the statutory deadline after your application, Section 7-3.6(D) requires the Secretary to issue you a Certificate of Hardship automatically, allowing the Building Commissioner to process your permit despite the missed decision.
Can I appeal a denial?
Yes. Section 7-3.7 lets an aggrieved applicant appeal to Suffolk Superior Court within 20 days after the determination is filed with the City Clerk. The court can annul, remand, or otherwise decree relief; costs are only assessed against a party who acted in bad faith.

Sources & Official References

Other rules in Boston

All Boston rules

Compare Boston to another location·View the Massachusetts historic preservation overview

Get notified when Historic-Cultural Monuments in Boston, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Historic-Cultural Monuments in Nearby Cities

How other cities in this county handle historic-cultural monuments.

Revere, MA
Some Restrictions