Alexandria, VA Hurricane Preparedness: Flood Elevation (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Elevation standard
Lowest floor at BFE plus 1 foot
Applies to
New/substantially improved buildings, Zones A & AE
Enforcing agency
T&ES floodplain administrator
Non-residential alternative
Dry-floodproofing, PE/architect certified
First-offense penalty
$200 civil violation (Sec. 11-207)
Subsequent-violation penalty
$500 per repeat violation

Summary

Alexandria requires new construction and substantially improved buildings in the FEMA-mapped Zone A or AE floodplain to elevate the lowest floor, including any basement, to at least one foot above the base flood elevation before the Department of Code Administration will issue a permit.

(A)Residential construction.(1)New construction or substantial improvement or any residential building or structure and their extensions and accessory buildings or structures in Zones A, AE, and with detailed base flood elevations shall have the lowest floor, including basement, elevated to or above the base flood elevation plus 1-foot.(2)No building permit for the substantial improvement of an existing residential building shall be at least one foot issued unless the building has the lowest floor (including the basement) elevated to or above the base flood elevation plus 1-foot.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 156 | Zoning: Supplement 103).

Full Breakdown

Alexandria's Zoning Ordinance regulates construction inside the FEMA-mapped floodplain under Article VI, Sec. 6-300 (Floodplain district), enforced by the city's floodplain administrator in the Department of Transportation and Environmental Services (T&ES). Sec. 6-307(A) requires that any new or substantially improved residential building, plus its extensions and accessory structures, sited in Zone A or Zone AE have its lowest floor, including any basement, elevated to or above the base flood elevation (BFE) plus one foot. No building permit for a substantial improvement to an existing residential structure may be issued unless that one-foot freeboard standard is met.

Non-residential buildings face the same BFE-plus-one-foot elevation rule under Sec. 6-307(B)(1), but may instead be dry-floodproofed with watertight walls and flood-resistant materials up to that same elevation, certified by a registered professional engineer or architect. 2-percent annual chance flood elevation, whichever is greater. Any fully enclosed space below the required elevation, including areas used only for parking, storage, or building access, must be built of flood damage-resistant materials and include at least two automatic flood vents sized to one square inch of opening per square foot of enclosed area, per Sec.

6-307(C). Mechanical, electrical, and plumbing equipment must likewise sit at or above BFE plus one foot. Every application must include a certification from a licensed architect or engineer confirming the design meets these anchoring, materials, and elevation standards before a permit issues.

Violations & Fines

Building without the required freeboard is enforced as a zoning violation, not just a permitting delay. Sec. 11-207(A)(8) classifies any violation of the floodplain district regulations under Sec. 6-300 as a class five civil violation, and Sec. 11-207(C)(5) sets the penalty at $200 for a first offense and $500 for each subsequent violation of the same requirement arising from the same facts, capped at $5,000 in cumulative penalties. A structure lacking a required elevation certificate is presumed in violation until the owner supplies it.

Frequently Asked Questions

How high above flood level must a new Alexandria home be built?
Sec. 6-307(A) requires the lowest floor, including any basement, of a new or substantially improved residential building in Zone A or AE to sit at or above the base flood elevation plus one foot. The city will not issue a building permit for a substantial improvement without proof this freeboard standard is met.
Can I finish out a basement below the flood elevation line?
No. Sec. 6-307(C) requires any enclosed space below the base flood elevation plus one foot to be built of flood-resistant materials, used only for parking, storage, or access, and fitted with flood vents sized at one square inch per square foot of enclosed area; it cannot be finished living space.
What happens if I build below the required elevation?
The city treats it as a class five civil violation of the floodplain district regulations under Sec. 11-207(A)(8), carrying a $200 penalty for a first offense and $500 for each later violation of the same requirement, and the structure is presumed noncompliant until an elevation certificate is filed.
Do commercial buildings have to elevate too?
Yes, under Sec. 6-307(B)(1) they face the same base-flood-elevation-plus-one-foot standard as houses, but non-residential buildings may instead be dry-floodproofed with watertight, flood-resistant construction certified by a licensed engineer or architect in lieu of elevating.

Sources & Official References

Other rules in Alexandria

All Alexandria rules

Compare Alexandria to another location·View the Virginia hurricane preparedness overview

Get notified when Flood Elevation in Alexandria, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.