Hamburg Village, NY Hurricane Preparedness: Flood Elevation (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Nonresidential lowest floor
At or above two feet above base flood elevation
Alternative
Watertight floodproofing below two feet above base flood elevation
Floodproofing design
Licensed professional engineer or architect
Manufactured home chassis
At or above two feet above base flood elevation
Aboveground tanks
Base flood elevation plus two feet, or anchored
Maximum fine
$250 per offense

Summary

In the Village of Hamburg, new and substantially improved nonresidential buildings in areas of special flood hazard must raise the lowest floor to two feet above the base flood elevation or be floodproofed watertight to that level. Chapter 146 sets the standard, and a licensed engineer or architect must certify any floodproofing.

§ 146-5. General standards. ... D. Nonresidential structures. The following standards apply to new and substantially improved commercial, industrial and other nonresidential structures located in areas of special flood hazard, in addition to the requirements in § 146-5A(1), Subdivision proposals, and § 146-5A(2), Encroachments, and § 146-5B, Standards for all structures: (1) Within Zones A1-A30, AE and AH, and also Zone A if base flood elevation data are available, new construction and substantial improvements of any nonresidential structure shall either: (a) Have the lowest floor, including basement or cellar, elevated to or above two feet above the base flood elevation; or (b) Be floodproofed so that the structure is watertight below two feet above the base flood elevation, including attendant utility and sanitary facilities, with walls substantially impermeable to the passage of water.

Full Breakdown

This page covers the nonresidential side of Chapter 146, Flood Damage Prevention, of the Code of the Village of Hamburg, adopted by the Board of Trustees on 4-15-2019. Chapter 146 addresses flooding and the base flood and does not use the word hurricane, so the rules below are the village's flood-elevation requirements for owners planning for storm flooding.

Section 146-5D applies to new and substantially improved commercial, industrial and other nonresidential structures in areas of special flood hazard. In Zones A1-A30, AE and AH, and Zone A if base flood elevation data are available, the owner has two choices: elevate the lowest floor, including basement or cellar, to or above two feet above the base flood elevation, or floodproof the structure so it is watertight below two feet above the base flood elevation, including attendant utility and sanitary facilities, with walls substantially impermeable to the passage of water. Structural components below the base flood level must resist hydrostatic and hydrodynamic loads and the effects of buoyancy.

In Zone AO the lowest floor must be above the highest adjacent grade at least as high as the depth number on the Flood Insurance Rate Map plus two feet, or at least three feet if no depth number is specified. Under § 146-5D(3), a licensed professional engineer or architect develops or reviews the floodproofing design, and a floodproofing certificate giving the elevation to which the structure is floodproofed goes to the local administrator.

Related elevation figures in § 146-5 include manufactured homes in Zones A1-A30, AE and AH, where the bottom of the chassis frame must be at or above two feet above the base flood elevation, and aboveground storage tanks, which must be anchored or installed at or above the base flood elevation plus two feet. In Zone A with no base flood elevation data, manufactured homes need reinforced piers no less than 36 inches in height above grade. Recreational vehicles must be on site fewer than 180 consecutive days or be fully licensed and ready for highway use.

Violations & Fines

Under § 146-3E, a violation of Chapter 146 is punishable on conviction by a fine of no more than $250 or imprisonment for not more than 15 days, or both, and each day of noncompliance is a separate offense. Work found noncompliant draws a stop-work order, and a structure without an approved variance under § 146-6 is reported to the Federal Emergency Management Agency.

Frequently Asked Questions

How high must a commercial building be raised in the Village of Hamburg?
Under § 146-5D(1), in Zones A1-A30, AE and AH, and Zone A with base flood elevation data, the lowest floor including basement or cellar must be at or above two feet above the base flood elevation, unless the building is floodproofed to that level.
Can a business floodproof instead of elevating?
Yes. Section 146-5D(1)(b) lets a nonresidential structure be floodproofed so it is watertight below two feet above the base flood elevation, with walls substantially impermeable to water. A licensed professional engineer or architect must develop or review the design and certify it.
What applies to a manufactured home?
Under § 146-5E(2), a manufactured home placed or substantially improved in Zones A1-A30, AE and AH must sit on a permanent foundation with the bottom of the chassis frame at or above two feet above the base flood elevation and be securely anchored.
Does the Village of Hamburg code mention hurricanes?
No. Chapter 146 speaks of flooding, the base flood and areas of special flood hazard, and the Board of Trustees sets the elevation standards in those terms. The elevation numbers in § 146-5 apply to any flood that reaches the mapped areas.

Sources & Official References

Other rules in Hamburg Village

All Hamburg Village rules

New York rules heatmap·Compare Hamburg Village to another location·View the New York hurricane preparedness overview

Get notified when Flood Elevation in Hamburg Village, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.