Key Facts

Minimum residential elevation
2 ft above base flood elevation
Mechanical equipment elevation
1 ft above base flood elevation
FIRM basis date
March 16, 2005 FEMA study
Non-mapped sites
2 ft above grade (1 ft if post-2006 subdivision)
Variance body
Environmental Board, LDC § 6-33

Summary

Tallahassee requires new residential construction in mapped flood hazard areas to sit at least two feet above the base flood elevation, per LDC § 6-62. The city bases its flood maps on FEMA's March 16, 2005 flood insurance study, and a development permit is required before construction begins.

(1)Residential construction. New construction and substantial improvement of any residential structure shall have the lowest floor, including basement, elevated no lower than two feet above the base flood elevation. Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate the unimpeded movements of floodwaters shall be provided in accordance with standards of subsection (3) of this section. All manufactured homes to be placed or substantially improved within zones A1—30, AH, and AE shall be elevated on a permanent foundation such that the lowest floor of the manufactured home is at least two feet above the base flood elevation and is securely anchored to an adequately anchored foundation system in accordance with the provisions of subsection 6-61(2). All equipment or mechanical items for new construction, and any substantial improvement of any residential structure or manufactured home, shall be at an elevation of at least one foot above the base flood elevation.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Land Development Code: Supplement 75 | Code of Ordinances: Supplement 75).

Full Breakdown

LDC § 6-11 adopts, by reference, the areas of special flood hazard identified in FEMA's flood insurance study for the city dated March 16, 2005, along with the accompanying flood insurance rate maps and any later revisions. Inside those mapped areas, § 6-62(1) requires new construction and substantial improvement of any residential structure to have its lowest floor, including any basement, elevated no lower than two feet above the base flood elevation; manufactured homes in zones A1-30, AH, and AE must sit on a permanent foundation at that same two-foot elevation, and all mechanical equipment for new or substantially improved residential structures must sit at least one foot above the base flood elevation.

Outside the mapped special flood hazard areas, § 5-87(5) still requires every permit application to show the finished floor elevation is at least two feet above the highest ground elevation within ten feet of the building, dropping to one foot if the site sits in a subdivision approved after April 1, 2006; the land use and environmental services administrator can reduce that standard only if the applicant proves an alternative drainage design keeps water away from the structure. Under § 6-32, a development permit is required before any development activity begins, and the permit holder must submit an elevation certification, prepared by a registered surveyor or engineer, at both the framing inspection and the final inspection.

The Environmental Board hears variance requests and appeals under § 6-33, weighing flood and erosion danger, the property's need for a waterfront location, and the effect on neighboring development before granting relief.

Violations & Fines

Building below the required elevation without an approved variance from the Environmental Board (§ 6-33) is a permit violation; the building official can issue a stop-work order under § 6-32(b) if the required elevation certification is missing or shows a deficiency, and work done before certification is submitted proceeds at the permit holder's own risk. Code-wide penalties under § 1-7 add a fine up to $500, up to 60 days in jail, or both.

Frequently Asked Questions

How high above flood level must a new Tallahassee home sit?
LDC § 6-62(1) requires the lowest floor, including any basement, to sit at least two feet above the base flood elevation in mapped special flood hazard areas. Mechanical and utility equipment must clear the base flood elevation by at least one foot.
What flood maps does Tallahassee use?
LDC § 6-11 adopts FEMA's flood insurance study for the city dated March 16, 2005, along with its flood insurance rate maps, as the official basis for special flood hazard areas, updated whenever FEMA issues a revision.
Can I get a variance from the flood elevation rule?
Yes. LDC § 6-33 lets the Environmental Board grant variances after weighing factors like flood danger, the necessity of a waterfront location, and effects on neighboring properties, and it can attach conditions to any variance it grants.
What if my lot isn't in a mapped flood zone?
LDC § 5-87(5) still requires new construction to have a finished floor at least two feet above the highest ground elevation within ten feet of the building, or one foot if the site is in a subdivision approved after April 1, 2006.

Sources & Official References

Other rules in Tallahassee

All Tallahassee rules

Florida rules heatmap·Compare Tallahassee to another location·View the Florida hurricane preparedness overview

Get notified when Flood Elevation in Tallahassee, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.