Barrow County, GA Landscaping Rules: Tree Removal & Heritage Trees (2026)
Tree removal permit rules in Barrow County, GA, sometimes called heritage tree, protected tree, or street tree ordinances, list which trees require a permit before you can cut them down.
Key Facts
- Governing law
- UDC Article VIII, Div. 3 (§§ 89-891 to 89-894)
- Clearing limit
- 10 feet beyond the specific construction footprint
- Root zone protection
- Barrier fencing required during construction
- Non-compliance penalty
- 5-year plat/site-plan denial (§ 89-892)
- Enforcement
- Planning and Community Development Department
- Max civil penalty
- $2,500.00 per day (§ 89-1447)
Summary
In unincorporated Barrow County, clear-cutting a residential subdivision lot is illegal. Grading may strip only the land needed for the home, driveway, utilities, septic system, road, deck or patio, plus a ten-foot margin around each. Every tree outside that footprint must stay standing, and contractors must fence off critical root zones with a barrier before equipment or materials arrive on site.
(a)Clear cutting of any lot in a residential subdivision is prohibited, except as noted below. On such lots, land area shall be cleared only as is necessary for purposes of the proper development of said lot. Clearing shall be limited to the specific development and an area not to exceed ten feet from the specific development, including areas for:(1)The placement of the individual home;(2)The placement of driveways and sidewalks;(3)The placement of utilities and detention ponds;(4)The placement of septic systems;(5)The placement of roads;(6)The placement of decks and patios; and(7)Proper drainage as required by the county.
Full Breakdown
The Unified Development Code (chapter 89) devotes Article VIII, Division 3 to tree conservation across every zoning district in unincorporated Barrow County. Section 89-893 flatly prohibits clear-cutting any lot in a residential subdivision; land may be cleared only as necessary for the home, driveways and sidewalks, utilities and detention ponds, septic systems, roads, and decks and patios, plus proper drainage, and clearing cannot extend more than ten feet beyond that specific construction footprint. The rule reaches every recorded residential lot in the county's subdivisions, not just larger tracts.
Section 89-892 carves out narrow exemptions: individual homeowners adding to an existing home, building accessory structures such as a pool or guest quarters, or removing diseased, dying or hazardous trees are not subject to the tree conservation article, but that exemption never reaches protective buffers along streams, creeks or reservoirs. Agricultural tree harvesting is exempt only if it follows the county's timber-harvesting notice rules and state law; a property that is systematically thinned or clear-cut outside a bona fide agricultural use, or harvested without following those rules, is barred from receiving a preliminary plat or project site plan for five years, a penalty only the board of commissioners can waive by majority vote.
Once construction starts, section 89-894 requires a valid tree-protection barrier, for example a four-foot orange safety fence, wide caution tape or a lumber fence, placed around the critical root zone of every tree marked to survive. No one may store building materials, dump solvents, park equipment or run heavy machinery inside that barricaded root zone while work is underway. The planning and community development department reviews the tree-save plan as part of the required landscaping plan submittal before any development approval is issued.
Violations & Fines
Tree conservation is enforced under the Development Code's general violation and penalty article. Clear-cutting a residential lot without meeting the section 89-893 exceptions, or damaging a marked critical root zone during construction, is a misdemeanor under section 89-1447 and can draw a civil penalty of up to $2,500.00 per day the violation continues. Illegal clear-cutting or unauthorized timber harvesting also blocks the property from getting a new preliminary plat or site plan for five years under section 89-892.
Frequently Asked Questions
Can I clear-cut my whole lot before building in unincorporated Barrow County?
Are individual homeowners exempt from the tree conservation rules?
What happens if a lot is illegally clear-cut in Barrow County?
How must trees be protected during construction?
Sources & Official References
Other rules in Barrow County
Compare Barrow County to another location·View the Georgia landscaping rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.