Tree removal permit rules in Tangipahoa Parish, LA, sometimes called heritage tree, protected tree, or street tree ordinances, list which trees require a permit before you can cut them down.

Key Facts

Governing law
Tangipahoa Parish Code § 36-113(c)
Protected buffer
25-foot perimeter undisturbed green space
Removal basis
Species, disease or decay only
Approval needed
Planning department pre-approval of removal plan
Violation remedy
Full native-species remediation planting under § 36-8(c)

Summary

Tangipahoa Parish requires major subdivisions and special use residential commercial developments to preserve a 25-foot perimeter buffer of undisturbed green space. Trees inside that buffer, or on individual lots within it, may only be selectively removed for reasons of species, disease or decay, and the planning department must pre-approve the specific tree removal plan before any cutting starts.

These county ordinances apply to unincorporated areas of Tangipahoa Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(c)All developments shall preserve a 25-foot perimeter buffer of undisturbed green space, which may be considered as part of the stormwater management area. There shall be a minimum stormwater management area requirement of 20 percent of the gross area of all special use residential commercial developments, which shall meet the following standards:(1)The buffer may only be disturbed or modified for access or infrastructure connectivity with the approval of the parish engineer.(2)Fill shall not be placed in any required buffer.(3)Selective removal of trees will be allowed in the 25-foot buffer and individual lots. Removal shall be based on tree species and disease or decay. The selected tree removal plan shall be pre-approved by the planning department prior to removal.

Full Breakdown

Section 36-113(c) requires every major subdivision and special use residential commercial development to preserve a 25-foot perimeter buffer of undisturbed green space, which can count toward the chapter's separate requirement that at least 20 percent of the development's gross area serve as stormwater management area. Within that buffer, and on individual lots that fall inside it, paragraph (3) allows only selective tree removal, and the removal has to be justified by tree species, disease or decay, not by convenience or development plans. Before any cutting happens, the developer must submit a tree removal plan and get it pre-approved by the parish planning department.

The same buffer cannot be disturbed or modified for anything else, such as access or infrastructure connectivity, without the parish engineer's separate approval under paragraph (1), and paragraph (2) bars placing fill in the buffer altogether. Removing trees outside this approved process carries consequences under Section 36-8(c): unauthorized removal within an undisturbed stormwater management area, or grubbing there before a land clearing permit issues, triggers a full vegetation remediation requirement, replacing the cleared area with a planting mix of Class A trees (minimum four-inch caliper, 18 feet tall), Class B trees and shrubs sized and spaced to the parish's remediation standards, bonded and watered for two years by the contractor. Section 36-10 separately restricts what species may be planted in these buffers to a parish-approved native list.

Violations & Fines

Clearing trees in a required stormwater management buffer without a pre-approved removal plan, or grubbing there before a land clearing permit issues, is remediated under Section 36-8(c): the responsible party must replant the disturbed area on a per-1,250-square-foot basis with a set mix of native Class A and Class B trees and shrubs, post a two-year plant warranty bond, and maintain the new plantings, or face additional fines from the parish.

Frequently Asked Questions

Can a developer clear-cut the required perimeter buffer in a Tangipahoa Parish subdivision?
No. Section 36-113(c) requires the 25-foot perimeter buffer to stay undisturbed, and only selective tree removal is allowed inside it, based on species, disease or decay, not general clearing. The specific removal plan must be pre-approved by the parish planning department before any trees come down.
Do I need a permit before removing trees in the development buffer?
Yes. Section 36-113(c)(3) requires the planning department to pre-approve the selected tree removal plan before removal, and separately, Section 36-111(b)(1) requires a land clearing permit for parcels of five acres or more, major subdivisions, and special use residential commercial developments.
What happens if trees are removed from a protected buffer without approval?
Section 36-8(c) requires full vegetation remediation: replanting the disturbed area with a set mix of Class A and Class B native trees and shrubs sized to the parish's standards, plus a two-year contractor bond and watering commitment, on top of any fines the violation triggers.

Sources & Official References

Other rules in Tangipahoa Parish

All Tangipahoa Parish rules

Compare Tangipahoa Parish to another location·View the Louisiana landscaping rules overview

Get notified when Tree Removal & Heritage Trees in Tangipahoa Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.