Key Facts

Permit issuer
Manager of Engineering Services or his/her designee
Fee
$25 per permit, plus cost of necessary tests
Covered work
Sidewalk, driveway apron, curb or gutter in a public right-of-way
Inspection notice
At least twenty-four (24) hours before pouring or laying
Exempt
Repair or replacement of less than eight (8) lineal feet of sidewalk
Historic districts
Brick sidewalks and Belgian block curbing

Summary

In East Brunswick Township, no one can construct or remove a sidewalk, driveway apron, curb or gutter within a public right-of-way without first obtaining a permit from the Manager of Engineering Services or his or her designee. Section 189-25 sets the fee at $25 per permit, plus the cost of any tests the Township deems necessary.

It shall be unlawful for any person to construct or remove or cause to be constructed or removed any sidewalk, driveway apron, curb or gutter or any part thereof within any public right-of-way in the Township of East Brunswick without first having obtained a permit to do so from the Manager of Engineering Services or his/her designee. ... A fee of twenty-five dollars ($25.) shall be charged for each permit, and in addition thereto, the applicant shall pay the cost of all tests which the Manager of Engineering Services or his/her designee deems necessary.

Full Breakdown

Article IV of Chapter 189, adopted 10-9-67 and amended by Ord. No. 08-11 on 7-7-08, controls private work in the public right-of-way. Section 189-23 makes it unlawful to construct or remove, or cause to be constructed or removed, any sidewalk, driveway apron, curb or gutter or any part of one within any public right-of-way in East Brunswick Township without a permit from the Manager of Engineering Services or his or her designee. This article is the Code's permit for that class of work; the sections read here cover sidewalks, aprons, curbs and gutters rather than structures placed in the right-of-way.

Section 189-24 requires the owner of the premises or his agent to apply on Township forms. The application gives the applicant's name and address, the name and address of the person doing the work and of the owner if different, the location of the premises, the estimated cost, and a line and grade plan showing the exact location against a street intersection or other fixed object, its width, its relationship to the grade of the street and adjacent property and, for a driveway apron, its slope or pitch. Section 189-25 charges $25 per permit, payable when the application is filed, with test costs paid before issuance.

Section 189-26 requires work to follow the current NJDOT Specification Manual and Township specifications, prompt replacement of anything removed, no blacktop over or on a concrete sidewalk, and replacement of the entire section of curb for a curb cut, with breaking and recapping of curbing specifically prohibited. New or replacement sidewalks in historic districts are brick, and curbing is Belgian block. Section 189-27 requires notice to the Department of Planning and Engineering at least twenty-four (24) hours before pouring or laying. Section 189-28 exempts initial installation in a major subdivision under performance guaranties and repair or replacement of less than eight (8) lineal feet of existing sidewalk. Excavating in or tunneling under a street needs a separate road opening permit under § 189-5.

Violations & Fines

Section 189-23 makes unpermitted construction or removal in the right-of-way unlawful. Sections 189-23 through 189-29 print no fine amount of their own. Section 189-26 specifically prohibits breaking and recapping curbing and placing or covering a concrete sidewalk with blacktop, and work that departs from the Township specifications on file with the Department of Planning and Engineering is outside the permit.

Frequently Asked Questions

Do I need a permit to replace a driveway apron in East Brunswick Township?
Yes. Section 189-23 makes it unlawful to construct or remove a driveway apron within a public right-of-way without a permit from the Manager of Engineering Services or his or her designee. The application under § 189-24 needs a line and grade plan that shows the apron's slope or pitch.
What does the right-of-way permit cost?
Section 189-25 charges $25 for each permit, paid when the application is filed. The applicant also pays the cost of all tests that the Manager of Engineering Services or designee deems necessary, and those test costs are paid before any permit is issued.
Is there a size exemption?
Section 189-28(B) exempts the repair or replacement of less than eight (8) lineal feet of an existing sidewalk from Article IV. Section 189-28(A) also exempts initial installation in a major subdivision where the work is covered by performance guaranties required by the approving authority.
Is digging in the street covered by the same permit?
No. Under § 189-5, no person can make an excavation in or tunnel under any street without a road opening permit. An emergency excavation can start without one if the application is made at the same time or as soon as practical, and the permit is then retroactive to the start date.

Sources & Official References

Other rules in East Brunswick

All East Brunswick rules

Compare East Brunswick to another location·View the New Jersey sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in East Brunswick, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Nearby Cities

How other cities in this county handle encroachment permits.

Edison, NJ
Some Restrictions