Key Facts

Permit required for
Storing building material/merchandise in the street
Permit duration
30 days, extendable
Width cap
Max 1/3 of roadway width blocked
Issuing authority
Permit issued under Section 148-6 procedure
Extra conditions
Public Works Superintendent may add safety terms

Summary

Anyone who wants to store building material, merchandise or other items on a Hackensack street or public place needs a permit first, under Code Section 148-24. The permit expires automatically after 30 days unless extended, and it can never authorize blocking more than one-third of the roadway's width at any point.

No person shall obstruct or permit the obstruction of any street or public place by the storage or placing of any building material or other material or merchandise thereon, or permit the same to remain longer than is necessary to convey the same on or into private property, unless a permit so to do shall first have been issued in accordance with the provisions of § 148-6 of this chapter. ... Permits granted hereunder shall in each case expire 30 days after the date of issuance, unless extended. No such permit shall be granted which permits the use or obstruction of more than 1/3 of the width of the roadway of any public street at any one point.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4592721; v20 updated 2026-01-06; through 01-06-2026).

Full Breakdown

Section 148-24, in Chapter 148's Article III (Obstructions and Encroachments), is Hackensack's mechanism for temporarily and lawfully placing material in the public right-of-way. The default rule is a flat prohibition: no one may obstruct a street or public place with stored building material, other material or merchandise, or let it sit there longer than needed to move it onto private property, unless a permit has first been issued under the general permitting procedure in Section 148-6. Once granted, the permit is time-limited: it expires 30 days after issuance unless the applicant obtains an extension, so a contractor staging materials for a renovation cannot treat an initial permit as open-ended.

The ordinance also caps how much of the street the permit can cover, limiting any single obstruction to no more than one-third of the roadway's width at any one point, protecting the remaining travel lanes. The application itself must state, in addition to the general information Section 148-6B requires, the kind and character of the material to be stored, its exact location, and the maximum length of time the obstruction will continue. Beyond those baseline terms, the Superintendent of Public Works can attach further conditions to any individual permit, including requirements to keep the sidewalk open for pedestrian travel and any other conditions deemed necessary for public safety and convenience, giving the City case-by-case control over how a right-of-way encroachment is staged.

Violations & Fines

Storing material in the right-of-way without the Section 148-24 permit, or beyond its 30-day term or the one-third roadway cap, is enforced under the Code's general penalty in Section 1-15: up to a $2,000 fine, up to 90 days' imprisonment, or up to 90 days of community service, with each day the unpermitted obstruction remains treated as a separate violation.

Frequently Asked Questions

Do I need a permit to store construction material on a Hackensack street?
Yes. Section 148-24 makes it unlawful to obstruct a street or public place with building material, other material or merchandise, or leave it there longer than necessary to move it onto private property, unless a permit has first been issued under Section 148-6. This applies to contractors and homeowners alike.
How long does a Hackensack right-of-way material permit last?
The permit automatically expires 30 days after it is issued unless the holder gets it extended. There is no indefinite version; a project running longer than a month needs to seek an extension before the initial 30-day window runs out under Section 148-24B.
How much of the street can I block with a permit?
No more than one-third of the roadway's width at any single point, even with a valid permit. Section 148-24B caps every permit at that limit so through-traffic and emergency access remain along the rest of the street width.

Sources & Official References

Other rules in Hackensack

All Hackensack rules

Compare Hackensack to another location·View the New Jersey sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Hackensack, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.