Hempstead, NY Solar Energy: Expedited Solar Permitting (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Hempstead Code § 86-12G(1)
Program adopted
Local Law No. 75-2015, eff. 10/9/2015
Statewide partner program
New York Solar Smart Program
Standard form
LIPA solar energy system fast track application
Ties to
NYSERDA Cleaner Greener Long Island plan
Timing rules
Same 90-day start, 1-year completion

Summary

Hempstead participates in the Long Island Power Authority's standardized 'solar energy system fast track permit application' as a partner community in the New York Solar Smart Program under § 86-12G(1), a program the Town adopted specifically to cut the inconsistent, municipality-by-municipality permitting delays that had slowed rooftop solar deployment on Long Island.

Legislative intent. It has been established that variations in the building permit application process between municipalities can be an impediment to the advancement of deploying solar energy on Long Island. For the benefit of the public and to promote the most efficient use of energy resources, the Town of Hempstead is a partner community in the New York Solar Smart Program, working to reduce impediments to solar installation and to enable solar market growth. The Long Island Power Authority's "solar energy system fast track permit application" is a standardized permit for use by all Long Island municipalities that simplifies and streamlines the permitting of small-scale photovoltaic systems and increases consistency and transparency in permitting. It is vital that the Town of Hempstead participate in that process.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4863878; v67 updated 2026-04-28; through 04-28-2026).

Full Breakdown

The Town Board adopted this fast-track framework by Local Law No. 75-2015, effective October 9, 2015, adding it to § 86-12, the same section that otherwise governs how the Building Inspector examines, approves or disapproves any building-permit application under § 86-12A. The legislative findings behind § 86-12G explain the problem the fast-track program solves: because building-permit processes had varied from one Long Island municipality to the next, contractors and homeowners faced inconsistent paperwork and delay when installing solar equipment across town lines. By adopting the Long Island Power Authority's uniform fast-track form, referenced operationally in § 86-12G(2), Hempstead lets a single standardized application move through its Building Department instead of a custom Town-specific solar form.

The program ties into the New York State Energy Research and Development Authority's Cleaner Greener Long Island Sustainability Plan, a state-level clean-energy initiative that coordinated the regional push for consistent permitting. Because the fast-track application is submitted as part of, not instead of, the regular building-permit process, ordinary timing rules still apply: work under the resulting permit must start within 90 days and finish within a year under § 86-13A and C. The Building Department retains its usual authority to approve or disapprove the underlying construction shown on the fast-track form, so participation in the state program streamlines paperwork without waiving the structural and safety review every other building permit receives.

Violations & Fines

Skipping the permit process, fast-track or otherwise, before installing a residential solar system violates § 86-9A and § 86-12G and carries the same Chapter 86 penalties as any other unpermitted construction under § 86-25B: $500 to $2,500 or up to 15 days in jail for a first offense, escalating to $3,000 to $10,000 for a third offense within five years, with each additional day a separate offense.

Frequently Asked Questions

What is Hempstead's fast-track solar permit program?
It is the Town's participation in the Long Island Power Authority's standardized solar energy system fast track permit application, adopted under § 86-12G by Local Law No. 75-2015. Instead of a custom Hempstead-only solar form, applicants submit the same streamlined document accepted across Long Island municipalities.
Does fast-track permitting skip the Building Department's review?
No. Section 86-12A still gives the Building Inspector authority to examine, approve or disapprove the application. The fast-track form standardizes the paperwork so it moves faster across Long Island towns, but the underlying construction still gets the Department's ordinary safety and code review.
Why did Hempstead adopt the LIPA fast-track form instead of its own?
The Town's own § 86-12G(1) findings explain that permitting differences between municipalities were slowing solar deployment on Long Island, so Hempstead became a New York Solar Smart Program partner and adopted the region-wide LIPA form to make permitting more consistent and transparent.

Sources & Official References

Other rules in Hempstead

All Hempstead rules

New York rules heatmap·Compare Hempstead to another location·View the New York solar energy overview

Get notified when Expedited Solar Permitting in Hempstead, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.