Hempstead, NY Solar Energy: Panel Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Hempstead Code § 86-12G(2)
Application form
LIPA solar energy system fast track permit
Fee basis
Estimated cost of construction, no cap
Fee amended
Local Law No. 20-2024, effective 4/2/2024
Work start deadline
90 days after issuance
First offense penalty
$500 to $2,500 or 15 days jail

Summary

A residential solar photovoltaic system or power wall in Hempstead needs a building permit, and the application must include the standardized fast-track permit form under § 86-12G(2). The Building Department charges a fee based on the estimated cost of construction under § 86-11EE, which the Town Board freed from a former fee cap in 2024.

Residential solar photovoltaic system. A building permit application for a residential solar photovoltaic system shall require the submission of a fast track permit application, based on the Long Island Power Authority's "solar energy system fast track permit application" pursuant to the New York State Energy Research and Development Authority's Cleaner Greener Long Island Sustainability Plan.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4863878; v67 updated 2026-04-28; through 04-28-2026).

Full Breakdown

Because a residential solar photovoltaic system counts as an installation requiring a building permit, an applicant files with the Building Inspector the same way as for any other construction project, but must also submit the Long Island Power Authority's standardized "solar energy system fast track permit application," per § 86-12G(2), rather than a jurisdiction-specific form. That single fast-track document is accepted under the New York State Energy Research and Development Authority's Cleaner Greener Long Island Sustainability Plan. Fees are calculated on the estimated cost of the solar installation itself; Local Law No.

20-2024, effective April 2, 2024, amended § 86-11EE to remove what had previously been a cap on that fee, so larger installations now pay proportionally more. As with other building permits, work under a solar permit must commence within 90 days of issuance and be completed within one year, or the permit is deemed abandoned under § 86-13A and C, and a supplementary permit is required to extend the timeline. The fast-track format is intended to reduce the paperwork burden compared with Hempstead's general application requirements under § 86-9B and C, such as duplicate plans, specifications and property surveys, while the Building Department still reviews plans against the same structural, electrical and roofing-load standards that apply to any other building-permit application.

Violations & Fines

Installing a residential solar photovoltaic system or power wall without first obtaining the required building permit violates § 86-9A and § 86-12G and is punishable the same as any other unpermitted construction under § 86-25B: $500 to $2,500 or up to 15 days in jail for a first offense, rising to $3,000 to $10,000 for a third offense within five years, with each day of the violation counted separately.

Frequently Asked Questions

Do I need a building permit to install solar panels on my house in Hempstead?
Yes. Section 86-12G(2) treats a residential solar photovoltaic system or power wall as work requiring a building permit, and the application must include the Long Island Power Authority's standardized fast-track permit form rather than a separate Town-only application.
How much does a Hempstead solar permit cost?
The fee is based on the estimated cost of construction. Section 86-11EE, as amended by Local Law No. 20-2024 effective April 2, 2024, removed the prior cap on this fee, so the amount charged now scales with the size and cost of the installation.
Is the fast-track form the only paperwork I need to submit?
The fast-track application streamlines the process, but the Building Department still reviews the installation under the Town's general building-permit standards, and larger or more complex projects can require the plans and specifications normally required under § 86-9B and C.

Sources & Official References

Other rules in Hempstead

All Hempstead rules

New York rules heatmap·Compare Hempstead to another location·View the New York solar energy overview

Get notified when Panel Permits in Hempstead, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.