Key Facts

Minimum lot size
5 acres
Setback from property lines
50 feet minimum
Height limit
25 feet
Equipment standard
UL-listed components required
Inspection
County building inspector, NEC compliance
Near-airport requirement
FAA Form 7460-1 if within 1 mile
Governing section
Surry County Code § 154.008(C)(62)

Summary

Unincorporated Surry County zones home and commercial solar arrays as a "Solar Energy System, Level 2" use under Board of Commissioners ordinance § 154.008(C)(62), setting a minimum lot size, setback, height cap, equipment listing, inspection and decommissioning rules that apply before a system is installed.

These county ordinances apply to unincorporated areas of Surry County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(62) Solar energy system, Level 2. ... (a) Site standards. 1. The minimum lot size for this type of use shall be five acres. 2. Structures and fixed equipment shall be setback at least 50 feet from all property lines and public rights-of-way. The Planning Board may require greater setbacks on a case-by-case basis. 3. Height. Structures, including mounted solar collection systems, shall not exceed a height of 25 feet (excludes utility poles and antenna constructed for project). The Planning Board may lower the maximum height on a case-by-case basis as site conditions warrant. 4. Electric solar collection system components must have a UL listing. 5. All solar collection systems shall meet state building code requirements and the National Electric Code and shall be inspected by a county building inspector.

Full Breakdown

Surry County's Table of Permitted Uses lists solar electric generation under NAICS 221114: systems under 6,000 square feet as an accessory use are permitted by right (P) in nearly every zoning district, while systems over 6,000 square feet require a special use permit (S) from the Board of Adjustment in several districts. Either way, § 154.008(C)(62) governs the physical build-out. The minimum lot size for a Level 2 solar energy system is five acres. Structures and fixed equipment must be set back at least 50 feet from all property lines and public rights-of-way, though the Planning Board can require a larger setback case by case.

Mounted solar collection structures cannot exceed 25 feet in height (utility poles and antennas built for the project are excluded), and the Planning Board may lower that cap based on site conditions. Every electric solar collection component must carry a UL listing, and the whole system must meet the state building code and National Electric Code and be inspected by a county building inspector before it can operate. If the system sits within one mile of an airport, the installer must file FAA Form 7460-1 with the FAA's regional office in Memphis, Tennessee, and placement is barred outright in historical districts such as the Village of Rockford. Screening from adjacent properties and road rights-of-way is also required, per § 154.015, with the Planning Board able to demand more extensive buffering.

Violations & Fines

A solar system installed without the required zoning permit, outside the five-acre minimum lot size, inside the 50-foot setback, or over the 25-foot height cap is a zoning violation under § 154.005-10, enforced by the Zoning Administrator's office. As with other use violations, each day of noncompliance is a separate offense: a warning citation carries 15 days to correct, then $50 for a first citation and $100 for each later citation on the same offense, with unpaid penalties collectible as a civil debt and court injunctions available under § 154.005-11.

Frequently Asked Questions

How big does my lot need to be for a solar array in Surry County?
Section 154.008(C)(62) sets a five-acre minimum lot size for a Level 2 solar energy system, along with a 50-foot setback from all property lines and public rights-of-way, which the Planning Board can extend on a case-by-case basis for a specific site.
Is there a height limit on solar panel structures?
Yes. Mounted solar collection structures cannot exceed 25 feet, excluding utility poles and antennas built for the project, though the Planning Board may lower that limit further depending on site conditions such as nearby residences or terrain.
Do solar panels need to be inspected before use?
Yes. The system must meet the state building code and National Electric Code and be inspected by a county building inspector, and every electric solar collection component must carry a UL listing before the installation can be approved for operation.
Can I install solar panels near the Village of Rockford or an airport?
No solar energy system may be placed in a historical district such as the Village of Rockford. If the site is within one mile of an existing airport, the installer must also notify the FAA using Form 7460-1 sent to the regional office in Memphis, Tennessee.

Sources & Official References

Other rules in Surry County

All Surry County rules

Compare Surry County to another location·View the North Carolina solar energy overview

Get notified when Panel Permits in Surry County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.