Key Facts

Residential permit fee
$26 flat (building)
Commercial permit fee
0.8% of contract + 4%, $104 min
Ground-mount height limit
8 feet maximum
Ground-mount location
Side or rear yard only
Unpermitted work penalty
Triple the permit fee

Summary

Taunton requires a building permit before any solar array goes up, plus a separate electrical permit, under City Code §§ 250-1 through 250-3. Ground-mounted panels must sit in a side or rear yard, stand no taller than eight feet, and be screened from neighbors. Installing without a permit triples the fee owed.

No person shall undertake, authorize, allow, or cause any work referenced in §§ 250-2 through 250-6, inclusive, to be done without first applying for and obtaining permits therefor. ... Use or Application Type of Permit Description Fee ... Commercial Building Solar panels/wind generators 0.8% of contract price plus 4% of permit fee ($104 minimum) ... Residential Building Solar panels/wind generators $26

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4508986; v12 updated 2025-09-22; through 09-22-2025).

Full Breakdown

The City treats solar installation as regulated construction work. Chapter 250, § 250-1 states that no person may undertake any work referenced in §§ 250-2 through 250-6 without first applying for and obtaining a permit, and the Building Inspections and Permits Fee Schedule at § 250-2 lists 'Solar panels/wind generators' as its own line item: a residential building permit costs a flat $26, while a commercial building permit runs 0.8% of the contract price plus a 4% technology surcharge, with a $104 minimum. A separate electrical permit is required under § 250-3, priced the same way for commercial work (0.8% of contract price plus 4%, $78 minimum) and at a flat $26 for residential work.

Placement is governed separately by § 440-805, Solar panels, in the Zoning Ordinance. Panels larger than two square feet are barred from any front yard and from any building face fronting a street, unless integrated into the building's construction, with an exception for roof-mounted arrays. Ground-mounted panels must sit in a side or rear yard only, may not exceed eight feet in height, must be screened from neighboring properties with fencing or a mix of evergreen and deciduous plantings, and count as accessory structures for setback purposes. Roof-mounted panels are preferred as an integrated surface layer; separate flush-mounted panels must go on a rear- or side-facing roof unless that is proven ineffective, and on a sloped roof they cannot project above the roof peak, or more than five feet above a flat roof.

Work done without pulling the permit first draws a fine under § 250-7 of three times the fee that would otherwise have applied, and the Building Commissioner may seek an injunction against continued work in addition to that fine.

Violations & Fines

Installing solar panels, ground- or roof-mounted, without first obtaining the building and electrical permits triggers a fine under § 250-7 equal to triple the fee that would otherwise apply, calculated on the same contract-price formula used for the original permit. The Building Commissioner may also pursue injunctive relief to halt unpermitted work, and panels that violate the yard, height or screening standards in § 440-805 can be ordered removed or relocated.

Frequently Asked Questions

Do I need a permit to install solar panels in Taunton?
Yes. City Code § 250-1 bars any work listed in the fee schedule, including solar panels, without first obtaining a permit, and both a building permit and an electrical permit are required before installation begins.
How much does a solar permit cost in Taunton?
A residential building permit is a flat $26; commercial installations pay 0.8% of the contract price plus a 4% surcharge, with a $104 minimum. Electrical permits follow the same formula with a $78 commercial minimum, or $26 flat for residential work.
Where can I put a ground-mounted solar array?
Only in a side or rear yard under § 440-805. It cannot exceed eight feet in height and must be screened from neighboring properties with fencing or a mix of evergreen and deciduous plantings.
What happens if I install solar panels without a permit?
Section 250-7 fines the owner three times the fee that would otherwise have applied, and the Building Commissioner can seek an injunction to stop the work.

Sources & Official References

Other rules in Taunton

All Taunton rules

Compare Taunton to another location·View the Massachusetts solar energy overview

Get notified when Panel Permits in Taunton, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.