Vermilion Parish, LA Solar Energy: Panel Permits (2026)
Key Facts
- Who issues
- The Police Jury, after building official and parish engineer review
- Farm threshold
- Generation capacity of at least 50 kilowatts (kW) direct current
- Permit fee
- 0.3 percent of the projected cost of construction
- Public meeting
- Notice published at least twice, first at least 30 days before
- Permit lifespan
- Expires one year from issuance unless construction has commenced
- Penalty
- Fine up to $500.00, up to 30 days in jail, per violation
- Denial appeal window
- 30 days to submit additional information or an amended plan
Summary
In unincorporated Vermilion Parish, a developer needs a Police Jury permit before building or expanding a solar farm of at least 50 kilowatts dc. The application goes to the parish building official, the fee is 0.3 percent of projected construction cost, and a public community meeting is required before approval.
(a)Prior to building, constructing, placing, establishing, expanding, or substantively altering the operation of a solar farm or wind farm, a permit must be obtained by the developer from the police jury. Permits shall be issued only after the plan therefore has been approved for in this chapter. ... (d)The permit application shall be submitted to the parish building official, and upon submission of a permit application the applicant shall pay a fee to the parish in the amount of 0.3 percent of the projected cost of the construction of the proposed farm. ... (f)The application and plan shall be reviewed by the parish building official. If approved by the building official, the application, plan and any comments by the building official shall be forwarded to the parish engineer for review. If approved by the parish engineer, the application, plan and any comments thereon shall be forwarded to the police jury for review and consideration. ... (j)A permit shall expire one year from the date of issuance unless the construction has commenced on the farm. After the expiration of a permit, the applicant may reapply.
Full Breakdown
Article II of Chapter 42 of the Vermilion Parish Code, adopted by Ord. No. 2024-O-05 on 5-15-2024, governs solar and wind farms in unincorporated Vermilion Parish. Sec. 42-20 defines a solar farm as land where a series of solar collectors is placed to generate photovoltaic power with a capacity of at least 50 kilowatts (kW) direct current or more. It states that the term does not mean one or more solar collectors intended to provide power for a single residential dwelling or commercial property, so the permit process below is aimed at farms, not rooftop panels on one home.
Sec. 42-21(a) requires the developer to obtain a permit from the Police Jury before building, constructing, placing, establishing, expanding or substantively altering a farm. The application includes a site plan showing all property in the project, all access roads, a drainage study, an environmental study and a traffic plan. Under subsection (b), the applicant holds at least one community meeting before permit approval. Notice must be published at least twice in the parish's official journal at the applicant's expense, with the first publication at least 30 days before the meeting, and an affidavit of publication goes to the parish.
The application is submitted to the parish building official with a fee of 0.3 percent of the projected cost of construction, figured on the entire project including buffer zones and access roads. If the parish has reason to believe actual costs exceed anticipated costs by ten percent or more, it can audit the costs and require a supplement permit fee. Review then runs in order: building official, then the parish engineer, then the Police Jury. A denial at any step comes with a written statement of reasons, and the applicant gets 30 days to submit more information or an amended plan, after which the Police Jury can grant the permit by majority vote.
A permit can be transferred or assigned only with the parish's prior written approval, and it expires one year from issuance unless construction has commenced, after which the applicant can reapply. Sec. 42-23 adds substantive standards, including a buffer setback of not less than 300 feet from the center of any adjacent public roadway, a decommissioning plan with financial assurance, and a maintenance plan.
Violations & Fines
Sec. 42-24 makes a violation of the solar and wind farm ordinance a misdemeanor punishable, upon conviction, by a fine of not more than $500.00, a prison term of not more than 30 days, or both, for each violation. Each day a violation exists is a separate offense. Sec. 42-23(g)(3) adds an administrative track for maintenance failures: after written notice, the permittee has five days to remediate, then is fined $500.00, and $500.00 for each day or part thereof that the deficiency continues.
Frequently Asked Questions
Do I need a Police Jury permit for panels on my own house?
How much is the solar farm permit fee?
Is a public meeting required?
What happens if the application is denied?
How long does a solar farm permit last?
Sources & Official References
Other rules in Vermilion Parish
Compare Vermilion Parish to another location·View the Louisiana solar energy overview