Margate, FL Swimming Pools & Spas: Pool Permits (2026)
Swimming pool permit rules in Margate, FL, also covering above-ground pools, in-ground pools, and spa installations, set fencing, barrier, alarm, and inspection requirements.
Key Facts
- Bond amount
- $500.00 cash bond
- Who posts it
- The pool contractor, at time of applying for the permit
- Effect on permit
- Condition precedent to the building permit
- Release trigger
- Certificate of occupancy issued by the city building department
- Property covered
- Sidewalks, curbs, gutters, streets, medians, alleyways, pipes, hydrants
- Leftover funds
- Held as completion bond; commission holds evidentiary hearing
Summary
In the City of Margate, Florida, a pool contractor must post a $500 cash performance bond with the city when applying for a pool permit. The bond is a condition precedent to the building permit and is held until a certificate of occupancy issues.
(a)All pool contractors obtaining pool permits for construction of swimming pools in the city shall at the time of applying for the pool permit place with the city a cash bond for performance in the amount of five hundred dollars ($500.00), which performance bond shall guarantee the reconstruction or repair of any and all city property which may be injured or damaged in any way by the pool contractor in the construction of the pool for which he is taking out the permit. ... Said cash bond shall further ensure that each pool constructed shall be properly constructed and completed. No cash bond shall be released until such time as a certificate of occupancy as provided by the South Florida Building Code is properly issued by the building department of the city. ... (b)The placing of the performance bond required by this section is a condition precedent to the issuance of a building permit for the construction and installation or repair of any pool in the city.
Full Breakdown
Section 9-6.1 of the Margate Code, titled swimming pool construction and repair, attaches a bond to every pool permit. Under subsection (a), all pool contractors obtaining pool permits for construction of swimming pools in the city must, at the time of applying for the pool permit, place a cash bond of five hundred dollars ($500.00) with the city. Subsection (b) makes the bond a condition precedent to the issuance of a building permit for the construction and installation or repair of any pool in the city. In practice that means the permit application and the $500 deposit travel together: without the bond, the building department has no authority to issue the permit.
The bond does two jobs. First, it guarantees the reconstruction or repair of any city property injured or damaged by the pool contractor while building the pool. The section names sidewalks, curbs, gutters, streets, medians, alleyways, water or sewer pipes and fire hydrants, and adds all other city property. Second, it ensures each pool is properly constructed and completed. No cash bond is released until the city building department properly issues a certificate of occupancy as provided by the South Florida Building Code.
If city funds are drawn to repair or rebuild city property, the leftover balance of the cash bond stays in place as a performance bond securing proper completion of the pool under the South Florida Building Code, and the city commission holds an evidentiary hearing to determine that.
Other building chapter rules sit alongside this one. Section 9-4 makes it unlawful to construct, alter or enlarge any structure in the City of Margate without a certificate of competency from the state Department of Business and Professional Regulation or the Broward County central examining board, and section 9-5 accepts permit applications only from those qualified persons or firms. Permit fees are set by resolution of the city commission under section 9-21, and the fee includes the inspection of the finished work. Section 9-6.1 dates to Ord. No. 2010-13, adopted October 20, 2010.
Violations & Fines
Section 9-6.1 has no penalty clause of its own. Building a pool without the bond and permit is a violation of the Margate Code, and the general penalty in section 1-8 applies: a fine not to exceed $500, up to 60 days in jail as provided in F.S. § 162.22, with each day a separate violation. Under section 9-21(4), work started without a valid permit is charged under the fee schedule set by commission resolution.
Frequently Asked Questions
How much is the bond for a pool permit in Margate?
Can Margate issue a pool building permit without the bond?
When does the contractor get the bond back?
What city property does the bond protect?
Sources & Official References
Other rules in Margate
Florida rules heatmap·Compare Margate to another location·View the Florida swimming pools & spas overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Pool Permits in Nearby Cities
How other cities in Broward County handle pool permits.