Swimming pool permit rules in Ridgewood, NJ, also covering above-ground pools, in-ground pools, and spa installations, set fencing, barrier, alarm, and inspection requirements.

Key Facts

Above-ground pool permit fee
$110
In-ground pool permit fee
$325
Pool barrier/fence permit (>6 ft)
$125
Fee due
Before permit is issued
Enforcing agency
Dept. of Building and Inspections
Appeals go to
Construction Board of Appeals

Summary

The Village of Ridgewood, Bergen County, requires a construction permit before building a residential swimming pool. The Department of Building and Inspections charges $110 for an above-ground pool and $325 for an in-ground pool, due before the permit issues.

The fee for a construction permit and other related permits shall be as set forth in Chapter 145, Fees, and shall be paid before the permit is issued. ... For swimming pools, the fee shall be: (a) Aboveground pool, $110. (b) In-ground pool, $325. (c) Swimming pool barriers and fences greater than six feet in height, $125.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4854397; v35 updated 2026-04-22; through 04-22-2026).

Full Breakdown

Under the Uniform Construction Code as administered locally, Village of Ridgewood Code § 125-3(A) requires that the fee for a construction permit and related permits be paid before the Construction Official's office issues the permit. Chapter 145's fee enumeration, § 145-6, sets the actual dollar figures collected under that authority: an above-ground pool permit costs $110, an in-ground pool permit costs $325, and a permit for swimming pool barriers or fences taller than six feet costs an additional $125. Because a residential pool touches more than one subcode, homeowners also pay separately for electrical work on pool, spa, or hot tub wiring and bonding, and for the plumbing subcode permit covering the pool's water supply and drain connections, both billed on their own line items in the same § 145-6 schedule.

The Building Subcode Official and other subcode officials named in § 125-1(A) review and inspect the work; plan review, when required, is credited toward the final construction permit fee under § 125-3(B). If the Construction Official denies or conditions a permit, the applicant can appeal to the Construction Board of Appeals established under § 125-2(A), a five-member board that includes a licensed architect or engineer and members qualified as plumbing and electrical subcode officials. Applicants should expect the pool permit, the barrier/fence permit if the fence exceeds six feet, and the related electrical and plumbing subcode permits to be filed and paid together before any digging or installation begins, since the Department will not issue the construction permit until its associated fee is paid in full.

Violations & Fines

Building a pool without the required construction permit exposes the owner to stop-work action and enforcement by the Department of Building and Inspections, and the Village can withhold a certificate of approval for the pool until the permit, barrier/fence permit, and any related electrical and plumbing subcode permits are obtained and their fees paid retroactively, in addition to normal permit fees.

Frequently Asked Questions

Do I need a permit for an above-ground pool in Ridgewood?
Yes. Village Code § 125-3(A) requires a construction permit before installation, and the fee schedule in § 145-6 sets the charge at $110 for an above-ground pool, payable before the Department of Building and Inspections issues the permit.
How much does an in-ground pool permit cost?
The construction permit fee for an in-ground pool is $325 under § 145-6. This is separate from the electrical and plumbing subcode fees charged for pool wiring, bonding, water supply, and drain work.
Does my pool fence need its own permit?
A pool barrier or fence taller than six feet requires its own permit under § 145-6, priced at $125, in addition to the pool construction permit itself.
Who do I appeal to if my pool permit is denied?
Village Code § 125-2(A) sends appeals from the enforcing agency's decisions to the Construction Board of Appeals, a five-member panel that includes a licensed architect or engineer and plumbing and electrical subcode-qualified members.

Sources & Official References

Other rules in Ridgewood

All Ridgewood rules

Compare Ridgewood to another location·View the New Jersey swimming pools & spas overview

Get notified when Pool Permits in Ridgewood, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.