Columbia, MO Tree Protection: Parkway Planting (2026)
Key Facts
- Permit required
- § 24-87, from public works director
- Utility clearance
- 4 feet minimum, horizontally
- Root barrier trigger
- Sidewalk-curb gap of 4 feet or less
- Hedge rule
- Barred between sidewalk and curb
- Overhead line clearance
- 5 feet at maturity
Summary
Columbia, Missouri regulates what residents can plant in the public street right-of-way, requiring a public works permit and setting minimum clearances from utilities, sidewalks, and curbs in Boone County.
(b)No tree shall be placed within four (4) feet, measured horizontally, of any underground utility.(c)Root barriers in accordance with city standards must be approved for any tree planting between the sidewalk and curb where the overall distance between the sidewalk and curb is four (4) feet or less, except for those indicated on the schedule of approved landscape materials as not requiring root barriers. In spaces greater than four (4) feet, the requirement of root barriers shall be determined based upon actual clearance and species of trees planted.(d)Landscape materials over thirty (30) inches in height measured from the top of curb shall be located so as not to cause sight distance obstructions from intersecting streets or private driveways. Hedges shall not be planted or maintained between the sidewalk and curb. General sight distance guidelines are on file in the public works department but shall be subject to local topographic conditions and traffic volumes.(e)No tree shall be planted under a utility line unless it is of a species which at maturity will provide a minimum of five (5) feet clearance between the apex of the tree and the lowest utility line. (Ord. No. 13969, § 1, 2-21-94)
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 138).
Full Breakdown
Columbia Code of Ordinances § 24-87 makes it unlawful to plant landscape material in the public street right-of-way without a permit from the director of public works. Section 24-92 sets the technical standards: no tree may be placed within four feet of an underground utility, root barriers meeting city standards are required for any tree planted between the sidewalk and curb where that gap is four feet or less, plantings over 30 inches tall can't block sight distance from intersections or driveways, hedges are barred entirely between sidewalk and curb, and trees under utility lines need a species clearing the lowest line by at least five feet at maturity.
Violations & Fines
Planting without the § 24-87 permit, or violating the § 24-92 spacing and sight-distance standards, lets the director of public works issue a stop-work order under § 24-90 and require removal or correction of noncompliant material.
Frequently Asked Questions
Do I need a permit to plant a tree in the parkway strip in Columbia, Missouri?
How close can a parkway tree be to a utility line in Columbia?
Sources & Official References
Other rules in Columbia
Compare Columbia to another location·View the Missouri tree protection overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.