Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing overlay
HPO Historic Preservation Overlay District
Design authority
Historic Preservation Commission review
Decision body
Common Council, within 45 days
COA validity
Expires after 1 year, extendable
Satellite dishes
Max 2 per lot, 1 meter diameter
Penalty
$10-$200 per day, § 315-136A

Summary

Buildings inside Burlington's HPO Historic Preservation Overlay District must follow the published "Burlington Historic Downtown Main Street District: Design Quality - Standards Guidelines" on top of the underlying zoning district's own rules. The Historic Preservation Commission, Plan Commission and Common Council apply those guidelines to every exterior alteration request under Zoning Code § 315-42.

District standards. District standards shall conform to those required in the underlying basic zoning district. In addition, the design guidelines as set forth in the publication titled "Burlington Historic Downtown Main Street District: Design Quality - Standards Guidelines," as amended, published by the Burlington Historic Downtown Main Street District, shall be used by the Historic Preservation Commission, Plan Commission, and Common Council as HPO District design standards and guidelines.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4997580; v29 updated 2026-07-07; through 07-07-2026).

Full Breakdown

Zoning Code § 315-42B makes the design guidelines a binding overlay on the underlying zoning district. Any exterior change to a structure inside the HPO District, including painting, an addition, or demolition, needs a certificate of appropriateness approved or conditionally approved by the Common Council under § 315-42E(1), which must act within 45 days of receiving the Historic Preservation Commission's recommendation; signage certificates instead go straight to the Building Inspector for final approval with no Council vote. A certificate of appropriateness lapses one year after it is granted if construction has not begun, though the Council can grant a good-cause extension of up to one more year under § 315-42E(5).

Satellite dishes in the district are capped at two per lot or dwelling unit, one meter in diameter, and must stay hidden from public streets when reception allows it; a dish on a mast over 12 feet tall needs a separate building permit. Section 315-42E(3)(a) even lets the Council waive the chapter's normal 50%-of-equalized-value cap on lifetime structural repairs (set generally at § 315-84) if the work keeps the building's historic character. Applications for a certificate of appropriateness must include architectural plans, elevations, color samples and material samples under § 315-139.

Violations & Fines

Altering a structure's exterior in the HPO District without an approved certificate of appropriateness, or demolishing a designated historic structure without Historic Preservation Commission review and Common Council approval, is a zoning violation. Under the chapter's general enforcement provision, § 315-136A, a violator forfeits not less than $10 nor more than $200 plus prosecution costs per offense, with each day a violation continues counted separately, and may be jailed up to 30 days for nonpayment.

Frequently Asked Questions

Do I need approval to repaint a historic downtown building in Burlington?
Yes. Painting counts as an exterior alteration under § 315-42E(1), so it needs a certificate of appropriateness from the Common Council, based on the Historic Preservation Commission's recommendation, before you start work.
What design guide governs Burlington's historic downtown?
The "Burlington Historic Downtown Main Street District: Design Quality - Standards Guidelines," adopted by reference in Zoning Code § 315-42B and applied by the Historic Preservation Commission, Plan Commission and Common Council alongside the underlying zoning district's standards.
How long is a certificate of appropriateness good for?
One year from the date it is granted. If construction has not started by then, the certificate becomes void unless the Common Council grants an extension of up to one more year for a showing of valid cause, per § 315-42E(5).

Sources & Official References

Other rules in Burlington

All Burlington rules

Compare Burlington to another location·View the Wisconsin zoning overlays & bonuses overview

Get notified when Downtown Design Guide in Burlington, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.