Apple Valley, MN Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
Building and mechanical work, as stated in the Minnesota State Building Code
Plumbing
Permit required under the Minnesota Plumbing Code
Plan review fee
65% of the building permit fee
Unused permit
Expires 180 days after issuance without substantial work
Extension
One extension, not to exceed 180 days
Penalty
Misdemeanor under § 150.99

Summary

In the City of Apple Valley, Minnesota, building and mechanical work needs a permit as the Minnesota State Building Code requires, and plumbing work needs one under the Minnesota Plumbing Code. The Building Inspection Division issues them, fees follow the appendix to Chapter 35, and exterior work must be finished within set numbers of days.

(A) General. Permits are required for building and mechanical work as stated in the Minnesota State Building Code. Permits are required for plumbing work regulated by the Minnesota Plumbing Code. (B) Expiration of permits. Permits for building and mechanical work shall be valid for a period of time as stated in the Minnesota State Building Code. Permits for plumbing work, or any other permit issued under this chapter, shall be valid for a similar time period as building and mechanical permits.

Full Breakdown

Section 150.03(A) of the Apple Valley Code of Ordinances requires permits for building and mechanical work as stated in the Minnesota State Building Code, and permits for plumbing work regulated by the Minnesota Plumbing Code. The City Council adopted the state code by reference in § 150.01, with one copy on file in the office of the City Clerk, so the list of work that needs a permit is the state code's list, applied inside the City of Apple Valley in Dakota County, Minnesota. Section 150.02 makes the Building Inspection Division the Department of Building Safety, with a state certified building official as the administrative authority and the City Council as the appointing authority.

Under § 150.03(B), building and mechanical permits are valid for the time stated in the state code, and plumbing permits or any other permit issued under Chapter 150 are valid for a similar time period. Section 150.07(D) adds that a permit expires 180 days from the date of issuance if no substantial work is completed under it.

Fees are paid before the permit issues. Section 150.04 sets them by the appendix to Chapter 35, adds a state permit surcharge remitted to the Minnesota Department of Labor and Industry under M.S. § 326B.148, and bases the fee on the valuation of the work, taken from the State of Minnesota Building Valuation Data, a cost estimating manual such as Means Building Cost Data, the applicant's valuation, or a city established valuation. A plan review fee of 65% of the building permit fee is paid when plans are submitted for all commercial building permits, all new single-family home permits, and all new apartment building and condominium permits.

Section 150.07 also sets completion deadlines for exterior work: 180 days for roofs, siding, replacement doors and windows, accessory structures and retaining walls on single-family property, and 365 days for new construction and additions to the primary home. Sheds, detached garages, decks and fences count as exterior structures. The Building Official can grant one extension of not more than 180 days for unavoidable delay. Exterior work done without a permit falls outside those dates, and the Building Official alone sets the completion and code compliance date.

Violations & Fines

Violation of any provision of Chapter 150 is a misdemeanor punishable as provided in § 10.99, and under § 150.99 the city building official or building inspectors can issue a citation in lieu of arrest or continued detention. Failing to finish exterior work inside the § 150.07 deadline, including any extension, is itself a violation of the chapter. Where work was done without a permit, the Building Official has sole authority to fix the completion and code compliance date.

Frequently Asked Questions

How does Apple Valley decide whether a project needs a building permit?
Section 150.03(A) sends the question to the Minnesota State Building Code, which the City Council adopted by reference in § 150.01. Building and mechanical work needs a permit as that state code states, and plumbing work needs one under the Minnesota Plumbing Code. Section 150.07 treats sheds, detached garages, decks, retaining walls and fences as exterior work when a building permit covers them.
How long is an Apple Valley building permit valid?
Section 150.03(B) makes building and mechanical permits valid for the time stated in the Minnesota State Building Code, and plumbing or other Chapter 150 permits valid for a similar period. Section 150.07(D) expires a permit 180 days after issuance if no substantial work has been completed, and § 150.07(B) allows one extension of not more than 180 days for unavoidable delay.
What fees come with a building permit in Apple Valley?
Section 150.04 requires the fee to be paid before the permit issues, sets amounts by the appendix to Chapter 35, and adds a state surcharge remitted to the Minnesota Department of Labor and Industry. The fee is based on the valuation of the work. Commercial, new single-family and new apartment or condominium permits also carry a plan review fee of 65% of the building permit fee.
How long do I have to finish exterior work under a permit?
Under § 150.07(A)(2), single-family roofs, siding, replacement doors and windows, accessory structures and retaining walls carry 180 days from issuance, while new construction and additions to the primary home carry 365 days. Commercial and industrial building exteriors are set by the Building Official. Failing to finish inside the deadline, including any extension, violates the chapter.

Sources & Official References

Other rules in Apple Valley

All Apple Valley rules

Compare Apple Valley to another location·View the Minnesota building safety overview

Get notified when Building Permits in Apple Valley, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.