Key Facts

Permit required
Yes, under adopted state building code
Completion deadline
18 months, extendable 12 more
First violation penalty
Up to $300 civil fine
Repeat violation penalty
Up to $500, per day
Farm/ranch exemption
Accessory structures under 1,000 sq ft

Summary

Billings requires a building permit for most new construction, additions, and alterations under the adopted state building code, with a narrow exemption for small farm and ranch accessory structures.

The following indicated sections of the Uniform Building Code are amended or added as follows: Section 106.2 is amended to add another exemption from a building permit: Farm and ranch accessory structures such as livestock barns, hay sheds, equipment storage, agriculture fences or similar uses directly related to agricultural operations. Structures are limited to one thousand (1,000) square feet and do not include habitable structures (i.e., residence, shop).

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 66 Update 2).

Full Breakdown

Billings adopts the current Montana Building Codes Bureau editions of the building, electrical, plumbing, and mechanical codes by reference under Sec. 6-201, and those codes govern permits for the erection, alteration, repair, moving, or demolition of buildings citywide. Permit fees follow the city's own council-set fee schedule rather than the model code's tables (Sec. 6-202). No plumbing, mechanical, or electrical permit can be issued until the building permit itself is issued (Sec. 6-303). Once issued, all exterior work on a new or altered structure must be completed within 18 months, with a possible 12-month extension for documented hardship (Sec. 6-304).

Violations & Fines

Building without a required permit, or missing the 18-month completion deadline, is a municipal infraction: up to $300 for a first offense, $500 per repeat, each day a separate violation (Sec. 18-1304).

Frequently Asked Questions

Does Billings require a permit for a farm shed?
No. Sec. 6-301 exempts farm and ranch accessory structures like hay sheds or livestock barns up to 1,000 square feet, set back 20 feet from property lines and other structures.
Can I get plumbing or electrical work permitted before the building permit?
No. Sec. 6-303 bars the city from issuing plumbing, mechanical, or electrical permits until the building permit for that structure is issued first.
What if I miss my building permit's completion deadline?
The building official can grant a one-time extension of up to 12 months for documented hardship such as product shortages or weather; otherwise it's a municipal infraction under Sec. 6-304.

Sources & Official References

Other rules in Billings

All Billings rules

Compare Billings to another location·View the Montana building safety overview

Get notified when Building Permits in Billings, MT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.