Cheektowaga, NY Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit review deadline
60 days from submission
Permit validity
1 year from issuance
Demolition start deadline
45 days after issuance
Extension available
up to 6 months, Inspector's discretion
Max penalty
$250 fine or 15 days jail, per day

Summary

Cheektowaga requires a permit from the Inspector before any construction, alteration, demolition or occupancy change, except non-structural repairs that involve no plumbing, electrical, heating or venting work. The Inspector must approve or deny an application within 60 days, and an issued permit authorizes work for one year.

No person, firm or corporation shall commence erection, construction, removal, enlargement, alteration, renovation, improvement, demolition, conversion or installation therein of any building or structure or change in nature the occupancy of any building or structure without first obtaining an appropriate permit from the Inspector, except that no permit shall be required for the performance of repairs which are not structural in nature and do not entail plumbing, electrical, heating or venting. ... The Inspector shall review or cause to be reviewed all applications for permits ... They shall approve or disapprove the application within 60 days from the date of submission of the application. ... A building/plumbing permit shall be considered authorization to work, for a period of one year after the date of its issuance, in accordance with the application, plans and specifications as approved by the Inspector.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4996449; v35 updated 2026-05-26; through 05-26-2026).

Full Breakdown

Under Cheektowaga Code § 70-11, no one may start erecting, altering, enlarging, demolishing, converting or changing the occupancy of a building or structure without first securing a permit from the Supervising Building and Plumbing Inspector. The only exception covers non-structural repairs involving no plumbing, electrical, heating or venting work. Applications go to the Inspector on Building Inspection Department forms and must include plans and specifications signed by the responsible designer; where state Education Law § 7302 applies, a licensed architect's or engineer's seal is required.

The Inspector reviews each application and must approve or deny it within 60 days of submission. Once approved and the required fees are paid, the Inspector issues the permit, and it authorizes work for one year from issuance; demolition work must start within 45 days. A project not started before the permit expires is deemed abandoned, though the Inspector may grant a postponement of up to six months if the owner asks within 30 days of expiration. If an 18-month-old permit's work still is not substantially complete, the owner may renew it once by filing a new application and paying the full current fee, and that renewal cannot be extended further.

Permits, approved plans and surveys must stay on the job site and be visible from the street throughout construction. The Inspector can revoke a permit for false statements in the application, issuance in error, work departing from approved plans, or failure to comply with a stop-work order.

Violations & Fines

Building without a permit, working outside approved plans, or ignoring a stop-work order under § 70-11D exposes the responsible party, contractor or owner to a fine of up to $250 or 15 days in jail under § 70-9B, with each day of continued violation a separate offense. The Inspector may also revoke the permit under § 70-11E and pursue court action to stop or correct the work under § 70-10.

Frequently Asked Questions

Does Cheektowaga require a permit for minor repairs?
No. Under § 70-11A(1), the Town does not require a permit for repairs that are not structural and do not involve plumbing, electrical, heating or venting work. Any structural change, new construction, demolition, or a change in a building's occupancy classification still needs a permit from the Inspector before work starts.
How long is a Cheektowaga building permit good for?
A building or plumbing permit authorizes work for one year from its issuance date under § 70-11C(1). Demolition permits require work to start within 45 days. If the project stalls, the Inspector may postpone the expiration up to six months, and after 18 months an unfinished permit can be renewed once at full fee.
What happens if I build without a Cheektowaga permit?
You are subject to enforcement under § 70-9, punishable by a fine of up to $250 or 15 days in jail, with every additional day of the violation charged as a separate offense. The Inspector can also issue a stop-work order under § 70-11D halting all work until conditions are corrected.

Sources & Official References

Other rules in Cheektowaga

All Cheektowaga rules

New York rules heatmap·Compare Cheektowaga to another location·View the New York building safety overview

Get notified when Building Permits in Cheektowaga, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Erie County handle building permits.

Buffalo, NY
Some Restrictions