Key Facts

Final CO decision deadline
30 days after completion notice
Inspection authority
any reasonable hour, § 70-12
Temporary CO available
for safely occupiable partial work
Records kept
permanent, public, per § 70-6

Summary

Cheektowaga inspects permitted work throughout construction and again at completion before issuing a certificate of occupancy. Once the finished work matches the approved plans, the Inspector must issue or deny the certificate within 30 days of the contractor's request for final inspection.

Before issuing a certificate of occupancy or compliance, the Inspector shall examine or cause to be examined all buildings, structures and sites for which an application has been filed for a building permit ... and he/she may conduct such inspections as he/she deems appropriate from time to time during and upon completion of the work for which a building permit or plumbing permit has been issued. ... When after final inspection it is found that the proposed work has been completed in accordance with applicable code ... the Inspector shall issue a certificate of occupancy/compliance ... The Inspector shall act to issue or deny a certificate of occupancy/compliance within 30 days after notification from the owner or contractor that all work has been completed and final inspections can be made.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4996449; v35 updated 2026-05-26; through 05-26-2026).

Full Breakdown

Cheektowaga Code § 70-16 sets the inspection stages between a building permit and the certificate of occupancy. ' The Building Inspection Department keeps a permanent record of every examination and inspection alongside any findings of violations, required separately by § 70-6A. At final inspection, if the work matches the approved application, plans and specifications and complies with the applicable code, the Inspector issues a certificate of occupancy or compliance; if not, the Inspector orders the work completed and withholds the certificate under § 70-16A(6). The Inspector must act, granting or denying the certificate, within 30 days after the owner or contractor notifies the Department that the work is finished and ready for final inspection.

A certificate issued through an error of fact or law is void. Where part of a project is finished and can be safely occupied without endangering life, health or welfare, the Inspector may issue a temporary certificate of occupancy covering that portion for a stated period, extendable for good cause. Separately, § 70-12 gives the Inspector a right of entry to any building, structure or premises at any reasonable hour to carry out these inspections, and an owner or tenant is deemed to have consented to that entry.

Violations & Fines

Occupying or using a building before a certificate of occupancy is issued violates § 70-16A(1) and is enforceable under § 70-9's penalty of up to $250 or 15 days in jail, with each day counted separately. A certificate obtained through a false application can be revoked, and continued occupancy without a valid certificate exposes the owner to the same fine and to court action to restrain illegal occupancy under § 70-10.

Frequently Asked Questions

When does Cheektowaga inspect a building under construction?
The Inspector examines the work under § 70-16A(4) during construction and again at completion, at whatever frequency he or she deems appropriate. The Inspector keeps a permanent record of every inspection and any violations found under § 70-6A, and the Building Inspection Department can accept certified inspection reports from other agencies.
How fast must Cheektowaga issue a certificate of occupancy?
Once the owner or contractor notifies the Building Inspection Department that work is complete and ready for final inspection, the Inspector must issue or deny the certificate within 30 days under § 70-16A(7). If the work does not match the approved plans, the certificate is withheld until it is corrected.
Can I occupy part of a building before the whole project is done?
Yes. Under § 70-16B, the Inspector may issue a temporary certificate of occupancy for a completed portion of a building if it can be occupied safely without endangering life, health or public welfare. It stays valid for the period the Inspector states and can be extended for good cause.

Sources & Official References

Other rules in Cheektowaga

All Cheektowaga rules

New York rules heatmap·Compare Cheektowaga to another location·View the New York building safety overview

Get notified when Building Inspections in Cheektowaga, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.